PMP practice once a day | don't get lost in the exam -7.26 (including agility + multiple choices)
2022-07-26 19:11:00 【Greenrad】
!PMP Latest exam notice !
1. Tentatively on 2022 year 6 month 25 The morning of Hold the first batch of exams ( I have finished the exam ).
2. Tentatively on 2022 year 7 month 30 On the afternoon of Sunday Hold the second batch of exams .
The first batch of today's exam
Come on , Go ashore
distance 【 The second batch of 】 Exams and
4 God
everyday 5 Avenue PMP Exercises help you get ashore PMP!!!

1、 The project manager goes to another country to implement the final deliverables Online process , After arrival , The project manager learned that , As the task is scheduled to be completed during local holidays , Critical resources will not be available , The delay in launching will put the delivery of the final project at risk . To avoid this problem , What should the project manager do at the beginning of the project ? ( )
A. establish - - Create a team project calendar and create a project schedule around this information
B. Ask all teams , No matter in which country , All follow the calendar of the headquarters
C. Develop an overtime budget to compensate for resources working during holidays
D. The impact of each national calendar is included in the risk register
【 answer 】:A
【 analysis 】: This question examines the knowledge points , Project schedule management - Develop schedule - Project Calendar . Dry key words : Local holidays . The project calendar specifies the working shifts of available working days that can carry out quarterly orders , In this way, the project calendar determines the public holiday of the whole project , You should include information about this local holiday in advance to create a schedule .
2、 The original planned duration of the project is 60 God , The customer asked for advance 10 Day delivery . The project manager finds that activities on the critical path cannot be paralleled , What should the project manager do ?( )
A. Apply for change , Follow up quickly on non critical paths
B. Apply for change , Follow up quickly on the critical path
C. Apply for change , To get resources to catch up on the critical path
D. Apply for change , To get resources to catch up on non critical paths
【 answer 】:C
【 analysis 】: This question examines the knowledge points : Progress compression .
There are only two ways to compress the construction period : Quickly follow up and catch up . It has been stated in the question stem that activities on the critical path cannot be carried out in parallel , So quick follow-up was ruled out , There is only one option left to rush , Rush needs to increase resources for activities on the critical path .
It should be noted that : To obtain more resources, you need to go through the change control procedure .
3、 When monitoring the progress of the project , You find that the milestones in the first phase will exceed the schedule and continue to the beginning of the second phase . however , At the end of - Stage milestones and submit their results , Unable to start the second stage . To meet the schedule of the first phase and deliver the expected results , What should you do as a project manager ? ( )
A Brainstorm with the project team and review several scenarios
B. Use the project calendar to calculate limited resources and project uncertainty
C. Develop a critical path , To determine the completion of the first - The longest time of the stage
D. Consider quickly following up on - - Stage
【 answer 】:D
【 analysis 】: This question examines the knowledge points : Progress compression .
According to the description of the title stem , The project has been postponed , And will affect the second stage , Schedule compression should be considered = Fast tracking , To reduce the impact .
Options AB Are not tools for schedule compression ; Options C It should be formulated at the planning stage , And in the monitoring phase, re analysis .
4、 Because the external consultant cannot complete the work before receiving the input from the company's internal experts , Cause the project to lag behind . Internal experts of the company have to work for multiple projects , The work of external consultants is affected , To avoid this happening , Which technology should be used in the planning stage ? ( )
A. Resource balance , Manage resource constraints
B. Rush to work , Add additional resources to the project
C. Fast track technology , Arrange and perform tasks , And reduce time
D. Cost reserve analysis , Fund unplanned costs
【 answer 】:A
【 analysis 】: analysis : This question examines the knowledge points : Resource balance .
book PMBOK The sixth edition P211:“ Resource balance is to achieve a balance between resource demand and resource supply , According to became an external consultant, the work was affected , It indicates that resource constraints are not considered when formulating the schedule , Failure to use resource balance has affected the work of external consultants , It indicates that resource constraints are not considered when formulating the schedule , There is no use of resource balance to manage constraints .
5、 The project manager calculates the time required for the activity through the critical path method to obtain the activity A need 4 Finish the activity in days B Must be active A When finished, start , need 3 Days time , Activities C In activity B When finished, start , need 2 Days time , Activities D In activity A Start = Days later, you can start to need 2 Days to complete . Activities E In activity C and D When finished, start , need 5 Days to complete . In the actual implementation process , Because of the risk , Cause activity D It was delayed for two days . Which of the following will happen in this case ? ( )
A The project can be completed on time
B. The project will be delayed by one day
C. The project will be delayed by two days
D. Coping activities D Catch up
【 answer 】:A
【 analysis 】: This question examines the knowledge points : Critical path method .
The critical path is A-B-C-E , 4+3+2+5=14 God , Not key activities D Originally there were 6 Floating time of days , So activities D Although delayed 2 Days, but it does not affect the overall progress of the project .
边栏推荐
- Basic module and example pytorch learning
- 2022 Shanghai safety officer C certificate operation certificate examination question bank simulated examination platform operation
- Huawei cloud · cloud sharing experts~
- Excellent JSON processing tool
- 场景之分页查询设计
- Operations research 69 | explanation of classic examples of dynamic planning
- 【Swoole系列3.1】进程、线程、协程,面试你被问了吗?
- Zbxtable 2.0 heavy release! 6 major optimization functions!
- How many pairs can an array of leetcode simple questions form
- FTP协议
猜你喜欢

JS刷题计划——数组

【Swoole系列3.1】进程、线程、协程,面试你被问了吗?

【考研词汇训练营】Day 14 —— panini,predict,access,apologize,sense,transport,aggregation

Redis学习笔记-2.客户端的使用

MySQL数据库命令大全

The class jointly built by famous oarsmen is new, and Professor qiuxipeng of Fudan University broadcast it live on Tuesday!

Arrangement of information security emergency plan

VPC nat (Sant, nant) experiment

Verification palindrome string II of leetcode simple question

How many pairs can an array of leetcode simple questions form
随机推荐
Basic module and example pytorch learning
【MySQL从入门到精通】【高级篇】(八)聚簇索引&非聚簇索引&联合索引
Tensor Rt的int8量化原理
[MySQL from introduction to proficiency] [advanced chapter] (VIII) clustered index & non clustered index & joint index
Multi thread learning notes -1.cas
Learn UML system modeling from me
JS question brushing plan - linked list
FTP protocol
ALV screen input option learning
网络协议:TCP/IP协议
Agenda express | list of sub forum agenda on July 27
Write a thesis and read this one
[postgraduate entrance examination vocabulary training camp] day 13 - reliance, expert, subject, unconscious, photograph, exaggeration, counter act
SSM整合-异常处理器和项目异常处理方案
[yuntu said] issue 246 digital asset chain - your God of digital asset property protection!
2022 Shanghai safety officer C certificate operation certificate examination question bank simulated examination platform operation
Is it safe to apply for public REITs account by mobile phone?
5 best overseas substitutes for WPS Office
Gongfu developer community is settled! On July 30!
Arrangement of information security emergency plan