Chapter 10 project stakeholder management
2022-06-24 22:30:00 【Cypress flousiana】

What is stakeholder management (P-377)— master
** Project stakeholder management (Stakeholder Management):** Requirements for project stakeholders 、 Identification of hopes and expectations , And meet their needs through communication management 、 The process of solving its problems .


One of the project stakeholder management processes “ Identify stakeholders ”( Start the process group )P-378
** Identify stakeholders :** Identify all personnel who can affect or be affected by the project 、 A group or organization , Analyze stakeholder expectations and impact on the project .
The role of this process :
Help the project manager to establish appropriate attention to various stakeholders or stakeholder groups .
It should be in the interest of the stakeholders 、 Influence and degree of participation in the project
Stakeholders should be identified throughout the process , Regularly review and update .

Identify stakeholders — Input : Procurement documents (P-379)– master
All parties to the contract are key project stakeholders . Other interested parties should also be ( Such as suppliers ) As a project stakeholder .
Identify stakeholders — Tools and technology : Stakeholder analysis (P-383)– master
** Stakeholder analysis :** Identify stakeholder interests 、 Expectation and influence , And link them to the purpose of the project .
Stakeholder analysis also helps to understand the relationships between stakeholders so that they can be used to build alliances and partnerships , Increase the likelihood of project success .
At different stages of a project or phase , Different influences should be exerted on the relationship between stakeholders .
Steps for stakeholder analysis (P-384)– master

Stakeholder classification model (P-384)– a key

Identify stakeholders — Output : Stakeholder register (P-379)– master

Project stakeholder management process II “ Planning stakeholder management ”( Planning process team )P-379
** Planning stakeholder management :** Based on the needs of the stakeholders 、 Analysis of benefits and potential impact on project success , Develop appropriate management strategies , In order to effectively mobilize stakeholders to participate in the whole project life cycle process .
The role of this process :
- Provide a clear and actionable plan for interaction with project stakeholders , To support the interests of the project .
Stakeholder management is to establish and maintain a good relationship between the project team and stakeholders , In order to meet the various needs and demands of stakeholders within the project boundary .
Planning stakeholder management ---- Based on the needs of the stakeholders 、 Analysis of benefits and potential impact on project success , Develop appropriate management strategies , To have
Effectively involve stakeholders throughout the project life cycle .
The role of this process :
- Provide a clear and actionable plan for interaction with project stakeholders , To support the interests of the project .
Stakeholder management is to establish and maintain a good relationship between the project team and stakeholders , In order to meet the various needs and demands of stakeholders within the project boundary .
Planning stakeholder management — Tools and technology : Analytical techniques (P-384)– a key

Planning stakeholder management — Output : Stakeholder management plan (P-380)– master
Stakeholder management plan ---- Define the management strategy required to effectively mobilize stakeholders .
In addition to the information in the stakeholder register , The stakeholder management plan usually also includes :
- Required and current involvement of key stakeholders ;
- Scope and impact of stakeholder change ;
- The interrelationship and potential intersection between stakeholders ;
- As the project progresses , Methods to update and optimize stakeholder management plans
- Stakeholder communication needs at this stage of the project
- Information that needs to be distributed to stakeholders , Including language 、 Format 、 Content and level of detail ;
- Reasons for distributing relevant information , And the possible impact on stakeholder participation ;
- The time frame and frequency of distributing the required information to stakeholders ;
The project manager should be aware of the sensitivity of the stakeholder management plan , And take appropriate precautions
The third part of the project stakeholder management process “ Managing stakeholder engagement ”( Execution process group )P404
** Managing stakeholder engagement :** Throughout the project life cycle , Communicate and collaborate with stakeholders , To meet their needs and expectations , Solve the actual problems , The process of promoting the reasonable participation of stakeholders in project activities .
The role of this process :
- Help the project manager improve the support from stakeholders , And minimize stakeholder resistance , Significantly improve the chances of project success
Managing stakeholder engagement includes the following activities :1、 Mobilize stakeholders to participate in the project at the right time ;2、 Managing stakeholder expectations ;3、 Identify and address stakeholder concerns that are not yet a problem as early as possible , In order to assess the relevant project risks ;4、 Clarify and resolve identified issues

Managing stakeholder engagement — Input : Change log (P-381)– master
The change log is used to record changes that occur during the project . These changes and their impact on the project timing should be discussed with the appropriate stakeholders 、 Communicate the impact of costs and risks
Managing stakeholder engagement — Tools and technology : Interpersonal skills (P-384)– master
Apply interpersonal skills to manage stakeholder expectations , for example : Building trust 、 Resolve conflicts 、 Listen actively 、 Overcome resistance to change
Managing stakeholder engagement — Tools and technology : Managerial skills (P-385)– master
Apply management skills to coordinate all parties to achieve project objectives , for example : Guide people to reach a consensus on their goals ; Exert influence to support the project ; Negotiate and reach a consensus ; Adjust organizational behavior , Acceptance of results .
Managing stakeholder engagement — Output : Problem log (P-381)– master
- The problem log should be dynamically updated with the emergence of new problems and the resolution of old problems .
- Three elements of the problem log : problem 、 Those responsible 、 Settlement period
- Problem logs are used to record and monitor the resolution of problems . It can be used to facilitate communication , Ensure a common understanding of the problem .
Project stakeholder management process IV “ Control stakeholder engagement ”( Monitoring process group )P-382
** Control stakeholder engagement :** Overall oversight of project stakeholder relationships , Adjust strategy and plan , To engage stakeholders in the process .
The role of this process :
- As the project progresses and the environment changes , Maintain and improve the efficiency and effectiveness of stakeholder participation activities .

Project stakeholder management ----ITTO Summary

边栏推荐
- Concurrency of heap memory allocation
- 系统测试主要步骤
- Detailed installation and use of performance test tool wrk
- Seven principles of software design
- Rotate the square array of two-dimensional array clockwise by 90 °
- 解决dataframe报错ValueError: Cannot take a larger sample than population when ‘replace=False‘
- Embedded development: tips and tricks -- clean jump from boot loader to application code
- 一个女孩子居然做了十年硬件。。。
- Description of transparent transmission function before master and slave of kt6368a Bluetooth chip, 2.4G frequency hopping automatic connection
- Genesis public chain and a group of encryption investors in the United States gathered in consensus 2022
猜你喜欢

leetcode:45. 跳跃游戏 II【经典贪心】

Embedded development: tips and tricks -- clean jump from boot loader to application code

嵌入式开发:技巧和窍门——干净地从引导加载程序跳转到应用程序代码

Detailed installation and use of performance test tool wrk

理想L9,智能座舱新潮流

L2 元年,Arbitrum Nitro 升级带来更兼容高效的开发体验

Information update on automatic control principle

Docker installs redis-5.0.12. Detailed steps

60 个神级 VS Code 插件!!

60 divine vs Code plug-ins!!
随机推荐
OA system -- save the verification code to session
Want to be a test leader, do you know these 6 skills?
What aspects should we start with in the feasibility analysis of dry goods?
Genesis公链与美国一众加密投资者齐聚Consensus 2022
Description of transparent transmission function before master and slave of kt6368a Bluetooth chip, 2.4G frequency hopping automatic connection
The leader of ERP software in printing industry
Learning notes 23-- basic theory of multi-sensor information fusion (Part I)
Common voting governance in Dao
Heartless sword Chinese English bilingual poem 003 The sea of books
Zero code can apply data visualization to enterprise management
Double linked list implementation
The process from troubleshooting to problem solving: the browser suddenly failed to access the web page, error code: 0x80004005, and the final positioning: "when the computer turns on the hotspot, the
解决dataframe报错ValueError: Cannot take a larger sample than population when ‘replace=False‘
Introduction, installation and use of postman tool
代理模式详解
直播软件app开发,左右自动滑动的轮播图广告
Publicity of the second batch of shortlisted enterprises! Annual Top100 smart network supplier selection
seven
You are using pip version 21.1.2; however, version 22.1.2 is available
Shutter precautions for using typedef