当前位置:网站首页>Building Survey [1]
Building Survey [1]
2022-06-24 23:08:00 【Star drawing question bank】
1. The general aiming method shall be ().
A. Precise aim 、 Correct aiming 、 Aim roughly
B. Aim roughly 、 Precise aim 、 Correct aiming
C. Correct aiming 、 Aim roughly 、 Precise aim
D. Aim roughly 、 Correct aiming 、 Precise aim
2. The principle to be followed in construction survey is : From the whole to the part 、().
A. Planning before implementation
B. Start with details and then expand
C. Control first and then break down
D. Break the part first and then control
3. The distance intersection method of setting out points is based on () To set out .
A. An angle and a distance
B. Two angles
C. Two distance
D. The difference between the two coordinates
4. The accuracy requirement of measurement work is ().
A. The more accurate, the better
B. Determine the appropriate accuracy index according to the needs of the project
C. Try to achieve as much accuracy as possible
D. No error is best
5. Under the same observation conditions , Multiple observations of the same quantity , The more observations , be
A. The accuracy of the arithmetic mean remains unchanged
B. The higher the accuracy of the observations
C. The higher the accuracy of the observed value and the arithmetic mean
D. The accuracy of the observations remains unchanged , The higher the accuracy of the arithmetic mean
6. In a picture 1:500 In the topographic map of ,AB The distance between two points on the graph is 0.332m, be AB The actual distance between two points is :()m
A.320
B.332
C.166
D.60
7. Two points at different elevations , The slope shall be two points () The ratio of the , Multiplied by 100%.
A. Height difference and its oblique distance ;
B. Horizontal distance and oblique distance
D. Height difference and horizontal distance ;
8. An operation before the reading in the basic operation of leveling at a measuring station ().
A. Rough leveling must be done well .
B. Instruments must be properly placed , Aim at the ruler , Accurate leveling work .
C. Instruments must be properly placed , Rough leveling , The work of aiming at the ruler .
D. We must do a good job of accurate leveling .
9. According to their nature, measurement errors can be divided into which two of the following ?
A. System error 、 Accidental error
B. Mean square error 、 Limit error
C. Permissible error 、 Negligent error
D. Average error 、 Relative error
10. Where the contour lines are sparse on a topographic map, the terrain is represented
A. Precipitous
B. Gentle
C. Is the horizontal plane
D. It is a slope with uniform slope
11. Contour offset is
A. Height difference between adjacent contour lines
B. Horizontal distance between adjacent elevation points
C. Horizontal distance between adjacent contour lines
D. Distance from contour line to geoid
12. When the measuring range is small , The surface of the survey area can be regarded as a plane , Its coordinates are commonly used
A. Astronomical and geographical coordinates
B. Geodetic coordinates
C. Independent plane rectangular coordinates
D. Gaussian plane rectangular coordinates
13. The layout form often used in urban traverse survey is
A. Conform to the conductor
B. Close the wire
C. Sight distance conductor
D. Branch conductor
14. The basic work of survey is to survey the known ()、 Horizontal angle and elevation .
A. Plane coordinates
B. Space distance
C. Horizontal distance
D. Spatial coordinates
15. The construction control network shall be established first for construction survey , Survey the main axis of the building , Then measure the height of the building according to the main axis
A. Detail point
B. The control points
C. Building baseline
D. Altitude
16. In the level , The correct relationship between the leveling tube axis and the sight axis is
A. None of the above
B. The axis of the level tube is parallel to the collimation axis
C. The axis of the leveling tube is perpendicular to the collimation axis
D. The axis of the level pipe intersects the collimation axis
17. In ordinary leveling , The relationship between the sum of height difference and the sum of forward-looking reading and rear-looking reading is
A.Σh\=Σa+ΣB
B. None of the above
C.Σh\=Σa-ΣB
D.Σh\=Σb-ΣA
18. During the construction of high-rise buildings , The special instruments used for the upward projection and measurement of the construction axis layer by layer are
A. Vertical alignment instrument
B. Theodolite
C. Level
D. Range finder
19. The plane position method of commonly used measuring points is rectangular coordinate method 、 Angle intersection method 、 Distance intersection method and ().
A. Forward intersection method
B. Polar coordinate method
C. Tangent offset method
D. Deflection angle method
20. Leveling is provided by level () Find the height difference between two points , And through the elevation of one of the known points , Calculate the elevation of the unknown point .
A. Horizontal line of sight
B. Collimation axis
C. Plumb line
D. The axis of the level pipe
21. In ordinary leveling , The relationship between the sum of height difference and the sum of forward-looking reading and rear-looking reading is
A.Σh\=Σa-ΣB
B. None of the above
C.Σh\=Σb-ΣA
D.Σh\=Σa+ΣB
22. The distance intersection method of setting out points is based on () To set out .
A. The difference between the two coordinates
B. Two distance
C. An angle and a distance
D. Two angles
23. Contour offset is
A. Distance from contour line to geoid
B. Height difference between adjacent contour lines
C. Horizontal distance between adjacent elevation points
D. Horizontal distance between adjacent contour lines
24. The layout form often used in urban traverse survey is
A. Close the wire
B. Branch conductor
C. Sight distance conductor
D. Conform to the conductor
25. When the measuring range is small , The surface of the survey area can be regarded as a plane , Its coordinates are commonly used
A. Gaussian plane rectangular coordinates
B. Independent plane rectangular coordinates
C. Astronomical and geographical coordinates
D. Geodetic coordinates
26. Two points at different elevations , The slope shall be two points () The ratio of the , Multiplied by 100%.
A. Horizontal distance and oblique distance
B. Height difference and horizontal distance ;
D. Height difference and its oblique distance ;
27. In a picture 1:500 In the topographic map of ,AB The distance between two points on the graph is 0.332m, be AB The actual distance between two points is :()m
A.166
B.60
C.332
D.320
28. The general aiming method shall be ().
A. Correct aiming 、 Aim roughly 、 Precise aim
B. Aim roughly 、 Correct aiming 、 Precise aim
C. Aim roughly 、 Precise aim 、 Correct aiming
D. Precise aim 、 Correct aiming 、 Aim roughly
29. Leveling is provided by level () Find the height difference between two points , And through the elevation of one of the known points , Calculate the elevation of the unknown point .
A. Plumb line
B. The axis of the level pipe
C. Collimation axis
D. Horizontal line of sight
30. The basic work of survey is to survey the known ()、 Horizontal angle and elevation .
A. Spatial coordinates
B. Horizontal distance
C. Plane coordinates
D. Space distance
31. Under the same observation conditions , Multiple observations of the same quantity , The more observations , be
A. The higher the accuracy of the observations
B. The accuracy of the arithmetic mean remains unchanged
C. The higher the accuracy of the observed value and the arithmetic mean
D. The accuracy of the observations remains unchanged , The higher the accuracy of the arithmetic mean
32. In the level , The correct relationship between the leveling tube axis and the sight axis is
A. The axis of the level pipe intersects the collimation axis
B. The axis of the leveling tube is perpendicular to the collimation axis
C. None of the above
D. The axis of the level tube is parallel to the collimation axis
33. The plane position method of commonly used measuring points is rectangular coordinate method 、 Angle intersection method 、 Distance intersection method and ().
A. Polar coordinate method
B. Deflection angle method
C. Tangent offset method
D. Forward intersection method
34. Where the contour lines are sparse on a topographic map, the terrain is represented
A. It is a slope with uniform slope
B. Is the horizontal plane
C. Precipitous
D. Gentle
35. An operation before the reading in the basic operation of leveling at a measuring station ().
A. Instruments must be properly placed , Rough leveling , The work of aiming at the ruler .
B. We must do a good job of accurate leveling .
C. Instruments must be properly placed , Aim at the ruler , Accurate leveling work .
D. Rough leveling must be done well .
36. The accuracy requirement of measurement work is ().
A. Determine the appropriate accuracy index according to the needs of the project
B. No error is best
C. Try to achieve as much accuracy as possible
D. The more accurate, the better
37. The principle to be followed in construction survey is : From the whole to the part 、().
A. Break the part first and then control
B. Control first and then break down
C. Planning before implementation
D. Start with details and then expand
38. During the construction of high-rise buildings , The special instruments used for the upward projection and measurement of the construction axis layer by layer are
A. Level
B. Range finder
C. Theodolite
D. Vertical alignment instrument
39. According to their nature, measurement errors can be divided into which two of the following ?
A. Average error 、 Relative error
B. Permissible error 、 Negligent error
C. System error 、 Accidental error
D. Mean square error 、 Limit error
40. In the level , The correct relationship between the leveling tube axis and the sight axis is
A. The axis of the level tube is parallel to the collimation axis
B. The axis of the leveling tube is perpendicular to the collimation axis
C. The axis of the level pipe intersects the collimation axis
D. None of the above
41. In ordinary leveling , The relationship between the sum of height difference and the sum of forward-looking reading and rear-looking reading is
A.Σh\=Σa+ΣB
B.Σh\=Σa-ΣB
C.Σh\=Σb-ΣA
D. None of the above
42. The general aiming method shall be ().
A. Correct aiming 、 Aim roughly 、 Precise aim
B. Aim roughly 、 Precise aim 、 Correct aiming
C. Aim roughly 、 Correct aiming 、 Precise aim
D. Precise aim 、 Correct aiming 、 Aim roughly
43. An operation before the reading in the basic operation of leveling at a measuring station ().
A. Instruments must be properly placed , Rough leveling , The work of aiming at the ruler .
B. Instruments must be properly placed , Aim at the ruler , Accurate leveling work .
C. We must do a good job of accurate leveling .
D. Rough leveling must be done well .
44. Leveling is provided by level () Find the height difference between two points , And through the elevation of one of the known points , Calculate the elevation of the unknown point .
A. Plumb line
B. Collimation axis
C. The axis of the level pipe
D. Horizontal line of sight
45. Under the same observation conditions , Multiple observations of the same quantity , The more observations , be
A. The higher the accuracy of the observations
B. The accuracy of the observations remains unchanged , The higher the accuracy of the arithmetic mean
C. The accuracy of the arithmetic mean remains unchanged
D. The higher the accuracy of the observed value and the arithmetic mean
46. According to their nature, measurement errors can be divided into which two of the following ?
A. Mean square error 、 Limit error
B. Permissible error 、 Negligent error
C. Average error 、 Relative error
D. System error 、 Accidental error
47. The layout form often used in urban traverse survey is
A. Sight distance conductor
B. Branch conductor
C. Conform to the conductor
D. Close the wire
48. During the construction of high-rise buildings , The special instruments used for the upward projection and measurement of the construction axis layer by layer are
A. Level
B. Theodolite
C. Range finder
D. Vertical alignment instrument
49. The construction control network shall be established first for construction survey , Survey the main axis of the building , Then measure the height of the building according to the main axis
A. Building baseline
B. Detail point
C. The control points
D. Altitude
50. The basic work of survey is to survey the known ()、 Horizontal angle and elevation .
A. Space distance
B. Horizontal distance
C. Spatial coordinates
D. Plane coordinates
51. The plane position method of commonly used measuring points is rectangular coordinate method 、 Angle intersection method 、 Distance intersection method and ().
A. Tangent offset method
B. Deflection angle method
C. Forward intersection method
D. Polar coordinate method
52. In a picture 1:500 In the topographic map of ,AB The distance between two points on the graph is 0.332m, be AB The actual distance between two points is :()m
A.166
B.332
C.60
D.320
53. Two points at different elevations , The slope shall be two points () The ratio of the , Multiplied by 100%.
A. Height difference and horizontal distance
B. Height difference and its oblique distance
C. Horizontal distance and oblique distance
D. Skew distance and its height difference
54. The accuracy requirement of measurement work is ().
A. No error is best
B. The more accurate, the better
C. Determine the appropriate accuracy index according to the needs of the project
D. Try to achieve as much accuracy as possible
55. Where the contour lines are sparse on a topographic map, the terrain is represented
A. Precipitous
B. Is the horizontal plane
C. Gentle
D. It is a slope with uniform slope
56. Contour offset is
A. Distance from contour line to geoid
B. Horizontal distance between adjacent elevation points
C. Height difference between adjacent contour lines
D. Horizontal distance between adjacent contour lines
57. The basic work of survey is to survey the known ()、 Horizontal angle and elevation .
A. Space distance
B. Plane coordinates
C. Horizontal distance
D. Spatial coordinates
58. According to their nature, measurement errors can be divided into which two of the following ?
A. System error 、 Accidental error
B. Permissible error 、 Negligent error
C. Mean square error 、 Limit error
D. Average error 、 Relative error
59. The layout form often used in urban traverse survey is
A. Branch conductor
B. Conform to the conductor
C. Sight distance conductor
D. Close the wire
60. The plane position method of commonly used measuring points is rectangular coordinate method 、 Angle intersection method 、 Distance intersection method and ().
A. Forward intersection method
B. Tangent offset method
C. Polar coordinate method
D. Deflection angle method
61. The accuracy requirement of measurement work is ().
A. The more accurate, the better
B. Try to achieve as much accuracy as possible
C. Determine the appropriate accuracy index according to the needs of the project
D. No error is best
62. An operation before the reading in the basic operation of leveling at a measuring station ().
A. We must do a good job of accurate leveling .
B. Rough leveling must be done well .
C. Instruments must be properly placed , Rough leveling , The work of aiming at the ruler .
D. Instruments must be properly placed , Aim at the ruler , Accurate leveling work .
63. In ordinary leveling , The relationship between the sum of height difference and the sum of forward-looking reading and rear-looking reading is
A.Σh\=Σa-ΣB
B.Σh\=Σb-ΣA
C.Σh\=Σa+ΣB
D. None of the above
64. In a picture 1:500 In the topographic map of ,AB The distance between two points on the graph is 0.332m, be AB The actual distance between two points is :()m
A.320
B.166
C.332
D.60
65. The construction control network shall be established first for construction survey , Survey the main axis of the building , Then measure the height of the building according to the main axis
A. The control points
B. Building baseline
C. Altitude
D. Detail point
66. Leveling is provided by level () Find the height difference between two points , And through the elevation of one of the known points , Calculate the elevation of the unknown point .
A. Collimation axis
B. Horizontal line of sight
C. The axis of the level pipe
D. Plumb line
67. Under the same observation conditions , Multiple observations of the same quantity , The more observations , be
A. The higher the accuracy of the observations
B. The accuracy of the arithmetic mean remains unchanged
C. The accuracy of the observations remains unchanged , The higher the accuracy of the arithmetic mean
D. The higher the accuracy of the observed value and the arithmetic mean
68. In the level , The correct relationship between the leveling tube axis and the sight axis is
A. The axis of the level pipe intersects the collimation axis
B. The axis of the level tube is parallel to the collimation axis
C. None of the above
D. The axis of the leveling tube is perpendicular to the collimation axis
69. The distance intersection method of setting out points is based on () To set out .
A. Two angles
B. Two distance
C. An angle and a distance
D. The difference between the two coordinates
70. During the construction of high-rise buildings , The special instruments used for the upward projection and measurement of the construction axis layer by layer are
A. Theodolite
B. Vertical alignment instrument
C. Range finder
D. Level
71. When the measuring range is small , The surface of the survey area can be regarded as a plane , Its coordinates are commonly used
A. Independent plane rectangular coordinates
B. Astronomical and geographical coordinates
C. Gaussian plane rectangular coordinates
D. Geodetic coordinates
72. Two points at different elevations , The slope shall be two points () The ratio of the , Multiplied by 100%.
A. Horizontal distance and oblique distance
C. Height difference and horizontal distance ;
D. Height difference and its oblique distance ;
73. The principle to be followed in construction survey is : From the whole to the part 、().
A. Start with details and then expand
B. Control first and then break down
C. Planning before implementation
D. Break the part first and then control
74. The general aiming method shall be ().
A. Precise aim 、 Correct aiming 、 Aim roughly
B. Correct aiming 、 Aim roughly 、 Precise aim
C. Aim roughly 、 Precise aim 、 Correct aiming
D. Aim roughly 、 Correct aiming 、 Precise aim
75. In ordinary leveling , The relationship between the sum of height difference and the sum of forward-looking reading and rear-looking reading is
A. None of the above
B.Σh\=Σb-ΣA
C.Σh\=Σa-ΣB
D.Σh\=Σa+ΣB
76. The plane position method of commonly used measuring points is rectangular coordinate method 、 Angle intersection method 、 Distance intersection method and ().
A. Tangent offset method
B. Deflection angle method
C. Polar coordinate method
D. Forward intersection method
77. Contour offset is
A. Distance from contour line to geoid
B. Horizontal distance between adjacent contour lines
C. Horizontal distance between adjacent elevation points
D. Height difference between adjacent contour lines
78. According to their nature, measurement errors can be divided into which two of the following ?
A. Mean square error 、 Limit error
B. Average error 、 Relative error
C. System error 、 Accidental error
D. Permissible error 、 Negligent error
79. The layout form often used in urban traverse survey is
A. Close the wire
B. Sight distance conductor
C. Branch conductor
D. Conform to the conductor
80. The distance intersection method of setting out points is based on () To set out .
A. The difference between the two coordinates
B. Two distance
C. Two angles
D. An angle and a distance
81. During the construction of high-rise buildings , The special instruments used for the upward projection and measurement of the construction axis layer by layer are
A. Vertical alignment instrument
B. Range finder
C. Level
D. Theodolite
82. In the level , The correct relationship between the leveling tube axis and the sight axis is
A. None of the above
B. The axis of the level pipe intersects the collimation axis
C. The axis of the leveling tube is perpendicular to the collimation axis
D. The axis of the level tube is parallel to the collimation axis
83. The accuracy requirement of measurement work is ().
A. Try to achieve as much accuracy as possible
B. Determine the appropriate accuracy index according to the needs of the project
C. The more accurate, the better
D. No error is best
84. Where the contour lines are sparse on a topographic map, the terrain is represented
A. It is a slope with uniform slope
B. Is the horizontal plane
C. Gentle
D. Precipitous
85. When the measuring range is small , The surface of the survey area can be regarded as a plane , Its coordinates are commonly used
A. Geodetic coordinates
B. Independent plane rectangular coordinates
C. Gaussian plane rectangular coordinates
D. Astronomical and geographical coordinates
86. In a picture 1:500 In the topographic map of ,AB The distance between two points on the graph is 0.332m, be AB The actual distance between two points is :()m
A.60
B.332
C.166
D.320
87. An operation before the reading in the basic operation of leveling at a measuring station ().
A. Instruments must be properly placed , Aim at the ruler , Accurate leveling work .
B. Instruments must be properly placed , Rough leveling , The work of aiming at the ruler .
C. We must do a good job of accurate leveling .
D. Rough leveling must be done well .
88. The general aiming method shall be ().
A. Aim roughly 、 Correct aiming 、 Precise aim
B. Aim roughly 、 Precise aim 、 Correct aiming
C. Correct aiming 、 Aim roughly 、 Precise aim
D. Precise aim 、 Correct aiming 、 Aim roughly
89. The principle to be followed in construction survey is : From the whole to the part 、().
A. Start with details and then expand
B. Planning before implementation
C. Control first and then break down
D. Break the part first and then control
90. The construction control network shall be established first for construction survey , Survey the main axis of the building , Then measure the height of the building according to the main axis
A. The control points
B. Detail point
C. Building baseline
D. Altitude
91. Under the same observation conditions , Multiple observations of the same quantity , The more observations , be
A. The higher the accuracy of the observations
B. The accuracy of the observations remains unchanged , The higher the accuracy of the arithmetic mean
C. The higher the accuracy of the observed value and the arithmetic mean
D. The accuracy of the arithmetic mean remains unchanged
92. During the construction of high-rise buildings , The special instruments used for the upward projection and measurement of the construction axis layer by layer are
A. Theodolite
B. Level
C. Vertical alignment instrument
D. Range finder
93. The distance intersection method of setting out points is based on () To set out .
A. Two distance
B. Two angles
C. The difference between the two coordinates
D. An angle and a distance
94. The general aiming method shall be ().
A. Aim roughly 、 Precise aim 、 Correct aiming
B. Correct aiming 、 Aim roughly 、 Precise aim
C. Precise aim 、 Correct aiming 、 Aim roughly
D. Aim roughly 、 Correct aiming 、 Precise aim
95. Under the same observation conditions , Multiple observations of the same quantity , The more observations , be
A. The accuracy of the arithmetic mean remains unchanged
B. The higher the accuracy of the observations
C. The accuracy of the observations remains unchanged , The higher the accuracy of the arithmetic mean
D. The higher the accuracy of the observed value and the arithmetic mean
96. Contour offset is
A. Horizontal distance between adjacent contour lines
B. Horizontal distance between adjacent elevation points
C. Distance from contour line to geoid
D. Height difference between adjacent contour lines
97. The principle to be followed in construction survey is : From the whole to the part 、().
A. Planning before implementation
B. Control first and then break down
C. Start with details and then expand
D. Break the part first and then control
98. According to their nature, measurement errors can be divided into which two of the following ?
A. Permissible error 、 Negligent error
B. System error 、 Accidental error
C. Mean square error 、 Limit error
D. Average error 、 Relative error
99. In a picture 1:500 In the topographic map of ,AB The distance between two points on the graph is 0.332m, be AB The actual distance between two points is :()m
A.332
B.166
C.320
D.60
100. Where the contour lines are sparse on a topographic map, the terrain is represented
A. It is a slope with uniform slope
B. Precipitous
C. Is the horizontal plane
D. Gentle
边栏推荐
- Paddledtx v1.0 has been released, and its security and flexibility have been comprehensively improved!
- C language operators and expressions
- 并发之共享模型管程
- [ROS play with turtle turtle]
- 2022年安全员-A证考题及答案
- canvas 实现图片新增水印
- 研究生宿舍大盘点!令人羡慕的研究生宿舍来了!
- 03_SpingBoot 核心配置文件
- Daily practice (22): maximum sum of continuous subarrays
- 2022年高处安装、维护、拆除考试模拟100题及模拟考试
猜你喜欢

How to integrate Huawei cloud function services in fluent

01_ Getting started with the spingboot framework

Environment configuration | vs2017 configuring openmesh source code and environment

Parental delegation mechanism
![[postgraduate entrance examination English] prepare for 2023, learn list8 words](/img/25/d1f2c2b4c0958d381db87e5ef96df9.jpg)
[postgraduate entrance examination English] prepare for 2023, learn list8 words

Cases of addition, deletion, modification and search of C # learning for two years and C # import and export (de duplication)

01_SpingBoot 框架入门

并发之共享模型管程

【nvm】

加分利器 不负所托 | 知道创宇获攻防演练防守方感谢信!
随机推荐
推送Markdown格式信息到釘釘機器人
Selection (027) - what is the output of the following code?
案例解析:用「度量」提升企业研发效能|ONES Talk
15 lines of code using mathematical formulas in wangeditor V5
并发之共享模型管程
Annotation
laravel 创建 service层
2022安全员-B证考试题库及答案
Spark 离线开发框架设计与实现
Daily practice (22): maximum sum of continuous subarrays
01_ Getting started with the spingboot framework
EPICS记录参考3 -- 所有记录都有的字段
Research and investment strategy report on China's building steel structure anticorrosive coating industry (2022 Edition)
Docker installation redis- simple without pit
研究生宿舍大盘点!令人羡慕的研究生宿舍来了!
Solution to the login error of tangdou people
Market trend report, technical innovation and market forecast of solar roof system in China
2022 simulated 100 questions and simulated examination of high-altitude installation, maintenance and demolition
Some updates about a hand slider (6-18, JS reverse)
docker-mysql8-主从