当前位置:网站首页>Knowledge points of 2022 system integration project management engineer examination: project cost management
Knowledge points of 2022 system integration project management engineer examination: project cost management
2022-06-12 08:48:00 【weixin_ forty-six million six hundred and nineteen thousand two】
Many candidates are preparing for the exam 2022 System integration project management engineer examination , I have arranged for you 2022 Knowledge points of system integration project management engineer examination : Project cost management , For everyone to prepare for the exam and review .
Each process of project cost management , Include :
Planning cost management : For planning 、 management 、 Spend and control project costs and make policies 、 Procedures and documentation .
Estimated cost : The process of approximately estimating the amount of money required to complete a project activity .
Budget making : Aggregate estimated costs for all individual activities or work packages , The process of establishing an approved cost baseline .
Control the cost : Monitor project status to update project budget 、 The process of managing cost baseline changes .
These processes not only interact with each other , It also interacts with processes in other areas of knowledge .
Earned value technology is needed for each planned activity 、 Work packages or control accounts identify these significant values , namely :
Planned value (Planned Value,PV).PV It is to plan to complete an activity or... Before a given time point WBS Budgeted cost of component work .
Earned value (Earned Value,EV).EV Is the budgeted cost of the work actually completed within a given time period .
actual cost (Actual Cost,AC).AC Is the actual total cost of actually completing the work within a given time period .
Cost deviation (Cost Variance,CV).CV be equal to EV reduce AC. The formula is :CV=EV-AC
Schedule deviation (Schedule Variance,SV).SV be equal to EV reduce PV. The formula is :SV=EV-PV
CV and SV It can be converted to reflect the cost and schedule of any project ( The performance of ) Efficiency index of .
Cost execution ( The performance of ) Index (Cost Performance Index,CPI).CPI be equal to EV and AC The ratio of the .CPI Is the most commonly used cost efficiency indicator . The formula is :CPI=EV/AC;CPI Value if less than 1 The actual cost exceeds the budget ,CPI If the value is greater than 1 The actual cost is lower than the budget .
Schedule execution ( The performance of ) indicators (Schedule Performance Index,SPI). Except for progress status ,SPI Also predict the completion date . Sometimes and CPI Used in conjunction to predict project completion estimates .SPI be equal to EV and PV The ratio of the . The formula is :SPI=EV/PV;SPI Value if less than l The actual progress is behind the planned progress ,SPI If the value is greater than 1 It means that the actual progress is ahead of the planned progress .
Prediction techniques include predicting the time point at that time based on known information and knowledge , Estimate and predict the future situation of the project .
BAC= On completion PV The sum of the
ETC Equal to the revised remaining work estimate determined by the project implementation organization . This estimate takes into account resource performance and productivity to date , It is a relatively accurate comprehensive estimation . There are two ways to calculate ETC:
Based on atypical deviations ( The current bias is seen as atypical , And the project team does not expect this kind of deviation in the future ) Calculation ETC.
ETC=(BAC-EV)
Based on typical deviations ( The current deviation is considered to represent the future deviation ) Calculation ETC.
ETC=(BAC-EV)/CPl
EAC It is the most likely overall estimate based on project performance and qualitative risk analysis .EAC When the work of a given project is completed , Plan activities 、WBS Expected or foreseeable final total estimate of the component or project .EAC Equal to the actual cost to date (AC) Add new... Provided by the implementing organization ETC.EAC Calculation formula :
EAC=AC+ETC
Completion performance index (To Complete Performance Index,TCPI) Represents the work value corresponding to the remaining budget per unit cost , The formula is :
TCPI=(BAC-EV)/(BAC-AC) or TCPI=(BAC-EV)/(EAC-AC)
Hot recommendation :2022 Application time and entry summary of the annual soft exam ( Every province in the country )
边栏推荐
- MES helps enterprises to transform intelligently and improve the transparency of enterprise production
- Loading circling effect during loading
- 【新规划】
- Shell basic syntax -- array
- Background location case 1
- [data storage] storage of floating point data in memory
- Engineers learn music theory (I) try to understand music
- 进制GB和GiB的区别
- 第七章-更灵活定位内存地址
- Regular expressions in JS
猜你喜欢

域名映射到指定IP

MSTP的配置与原理

FDA审查人员称Moderna COVID疫苗对5岁以下儿童安全有效

Py & go programming skills: logic control to avoid if else

Display the remaining valid days according to the valid period

Regularization to limit the number of digits after the decimal point of an input number

【数据存储】浮点型数据在内存中的存储

Database foundation -- normalization and relational schema

Centso8 installing mysql8.0 (Part 2)

《MATLAB 神經網絡43個案例分析》:第7章 RBF網絡的回歸--非線性函數回歸的實現
随机推荐
Analysis of 43 cases of MATLAB neural network: Chapter 8 prediction of GRNN Network - Freight Volume Prediction Based on generalized regression neural network
ctfshow web4
深拷贝与浅拷贝的区别
2022.6.11-----leetcode.926
Error: ER_ NOT_ SUPPORTED_ AUTH_ MODE: Client does not support authentication protocol requested ... ...
[open source project] easycmd command graphical software
When the uniapp page jumps with complex data parameters.
Regular expressions in JS
R loop assignment variable name
Why should enterprises implement MES? What are the specific operating procedures?
Knee joint
Configuration and principle of MSTP
Webrtc series - mobile terminal hardware coding supports simulcast
Wechat applet image saving function
Box model border
Only use MES as a tool? Looks like you missed the most important thing
Dynamically create and submit forms
Handling abnormal data
Analysis of 43 cases of MATLAB neural network: Chapter 7 regression of RBF Network -- Realization of nonlinear function regression
【动态内存管理】malloc&calloc和realloc和笔试题和柔性数组