当前位置:网站首页>Knowledge points of 2022 system integration project management engineer examination: project cost management
Knowledge points of 2022 system integration project management engineer examination: project cost management
2022-06-12 08:48:00 【weixin_ forty-six million six hundred and nineteen thousand two】
Many candidates are preparing for the exam 2022 System integration project management engineer examination , I have arranged for you 2022 Knowledge points of system integration project management engineer examination : Project cost management , For everyone to prepare for the exam and review .
Each process of project cost management , Include :
Planning cost management : For planning 、 management 、 Spend and control project costs and make policies 、 Procedures and documentation .
Estimated cost : The process of approximately estimating the amount of money required to complete a project activity .
Budget making : Aggregate estimated costs for all individual activities or work packages , The process of establishing an approved cost baseline .
Control the cost : Monitor project status to update project budget 、 The process of managing cost baseline changes .
These processes not only interact with each other , It also interacts with processes in other areas of knowledge .
Earned value technology is needed for each planned activity 、 Work packages or control accounts identify these significant values , namely :
Planned value (Planned Value,PV).PV It is to plan to complete an activity or... Before a given time point WBS Budgeted cost of component work .
Earned value (Earned Value,EV).EV Is the budgeted cost of the work actually completed within a given time period .
actual cost (Actual Cost,AC).AC Is the actual total cost of actually completing the work within a given time period .
Cost deviation (Cost Variance,CV).CV be equal to EV reduce AC. The formula is :CV=EV-AC
Schedule deviation (Schedule Variance,SV).SV be equal to EV reduce PV. The formula is :SV=EV-PV
CV and SV It can be converted to reflect the cost and schedule of any project ( The performance of ) Efficiency index of .
Cost execution ( The performance of ) Index (Cost Performance Index,CPI).CPI be equal to EV and AC The ratio of the .CPI Is the most commonly used cost efficiency indicator . The formula is :CPI=EV/AC;CPI Value if less than 1 The actual cost exceeds the budget ,CPI If the value is greater than 1 The actual cost is lower than the budget .
Schedule execution ( The performance of ) indicators (Schedule Performance Index,SPI). Except for progress status ,SPI Also predict the completion date . Sometimes and CPI Used in conjunction to predict project completion estimates .SPI be equal to EV and PV The ratio of the . The formula is :SPI=EV/PV;SPI Value if less than l The actual progress is behind the planned progress ,SPI If the value is greater than 1 It means that the actual progress is ahead of the planned progress .
Prediction techniques include predicting the time point at that time based on known information and knowledge , Estimate and predict the future situation of the project .
BAC= On completion PV The sum of the
ETC Equal to the revised remaining work estimate determined by the project implementation organization . This estimate takes into account resource performance and productivity to date , It is a relatively accurate comprehensive estimation . There are two ways to calculate ETC:
Based on atypical deviations ( The current bias is seen as atypical , And the project team does not expect this kind of deviation in the future ) Calculation ETC.
ETC=(BAC-EV)
Based on typical deviations ( The current deviation is considered to represent the future deviation ) Calculation ETC.
ETC=(BAC-EV)/CPl
EAC It is the most likely overall estimate based on project performance and qualitative risk analysis .EAC When the work of a given project is completed , Plan activities 、WBS Expected or foreseeable final total estimate of the component or project .EAC Equal to the actual cost to date (AC) Add new... Provided by the implementing organization ETC.EAC Calculation formula :
EAC=AC+ETC
Completion performance index (To Complete Performance Index,TCPI) Represents the work value corresponding to the remaining budget per unit cost , The formula is :
TCPI=(BAC-EV)/(BAC-AC) or TCPI=(BAC-EV)/(EAC-AC)
Hot recommendation :2022 Application time and entry summary of the annual soft exam ( Every province in the country )
边栏推荐
- 2022.6.11-----leetcode.926
- Centso8 installing mysql8.0 (Part 2)
- In the era of intelligent manufacturing, how do enterprises carry out digital transformation
- 【新规划】
- Dynamically create and submit forms
- Regular verification user name
- Where does the driving force of MES system come from? What problems should be paid attention to in model selection?
- Wechat applet image saving function
- Background position position NOUN
- Regular expressions in JS
猜你喜欢

【进阶指针二】数组传参&指针传参&函数指针&函数指针数组&回调函数

【进阶指针一】字符数组&数组指针&指针数组

了结非对称密钥

Oracle installation details (verification)

(p17-p18) define the basic type and function pointer alias by using, and define the alias for the template by using and typedef

Where does the driving force of MES system come from? What problems should be paid attention to in model selection?

《MATLAB 神经网络43个案例分析》:第7章 RBF网络的回归--非线性函数回归的实现
![(node:22344) [DEP0123] DeprecationWarning: Setting the TLS ServerName to an IP address is not permit](/img/c1/d56ec09663857afa52f20848aeadac.png)
(node:22344) [DEP0123] DeprecationWarning: Setting the TLS ServerName to an IP address is not permit

域名映射到指定IP

ctfshow web4
随机推荐
Engineers learn music theory (I) try to understand music
【sklearn学习】LightGBM
【动态内存管理】malloc&calloc和realloc和笔试题和柔性数组
Principle and configuration of MPLS
This article is required for the popularization of super complete MES system knowledge
Wechat applet image saving function
《MATLAB 神经网络43个案例分析》:第7章 RBF网络的回归--非线性函数回归的实现
Graphic analysis of viewbox in SVG
Py & go programming skills: logic control to avoid if else
RuntimeError:Input and parameter tensors are not at the same device, found input tensor at cuda:0 an
Background position position NOUN
X64dbg debugging exception_ ACCESS_ VIOLATION C0000005
处理异常数据
Loading font component loading effect
At present, MES is widely used. Why are there few APS scheduling systems? Why?
了结非对称密钥
JS to refresh the page after loading
Where does the driving force of MES system come from? What problems should be paid attention to in model selection?
Specify 404 and 500 error reporting pages.
FDA reviewers say Moderna covid vaccine is safe and effective for children under 5 years of age