Project change management
2022-06-21 23:19:00 【straight left】
Change is inevitable , But it needs to be standardized .
Changes often occur in the process of information system engineering construction , Many project failures are caused by improper handling of changes . Changes are positive and negative , Good change management can improve the quality of the project 、 speed of progress 、 Cost management is more effective .
One 、 The basic concept of project change management
The essence of change management , It is based on the increasingly rich project cognition in the process of project promotion , Constantly adjust the direction of project efforts and resource allocation , Meet the needs of the project to the greatest extent , Enhance project value .
1、 Reasons for project change
Negligence or negligence
Value added change
Emergency plan or avoidance plan
Perform passive adjustments resulting from inconsistencies with the benchmark
External events
2、 Project change classification
1) According to the nature of the change : major alteration 、 Important changes 、 General changes . Control through different approval permissions .
2) According to the urgency : Emergency change 、 Non urgent change . Through different change processing processes .
3) Divide according to the change contents , It can be divided into several sub industries , Different contents adopt different control methods .
3、 Meaning of project change
Change management is to make the project benchmark consistent with the actual implementation of the project , A set of management methods to deal with project changes . The result is either to reject change , Or adjust the project benchmark .
From the perspective of value-added resources , The substance of the change , Is to adjust the way resources are allocated , Or use the reserved resources in the project , Meet the needs of the project .
Two 、 Project change management principles
The principle of change management is project benchmarking 、 Standardization of change management process . Including the following :
1、 Benchmark management
Benchmark is the basis for change . After the initial benchmark is established , After each change passes the review , Should be re benchmarked .
2、 Change control flow :
Establish or select a change management process that meets the needs of the project , All changes must be controlled according to this control process .
3、 Clarify the organization and division of labor
4、 Evaluate the possible impact of the change
5、 Keep the relevant documents generated by the change properly
3、 ... and 、 Change management organization and working procedures
1、 Organization
Advocate decentralized operation , Specify the resource allocation convention . Generally, the agreed work is performed by the project implementer according to the benchmark , The operation authority is delegated to the project manager ; The reserve resources of the project are unauthorized , Support project change operations , The right belongs to the project sponsor , The representative is the management committee .
1)CCB
Project control committee or configuration control committee , Or similar organizations . Is the representative of all rights and interests of the project , Responsible for deciding which changes to accept . It is composed of relevant personnel , It usually includes decision makers of users and implementers .
Be careful CCB It's a decision-making body , It's not an operating agency , Usually only responsible for review , Decide whether to change , But don't propose a change plan .
2) project manager
The project manager is entrusted by the owner to be responsible for the operation process of the project , Rights are derived from the project charter , The authority to schedule resources is usually defined by benchmarks . The reserved resources not included in the benchmark can only be used after being approved by the authorized person .
3) The role of the project manager in change
Respond to change requests ; Evaluate the impact of the change on the project and the response plan ; Transform requirements from technical requirements to resource requirements , For the authorizer to make decisions ; Implement according to the review results , Adjustment datum ; Ensure that project benchmarks reflect project implementation .
2、 Working procedure
1) Propose and accept changes
2) Preliminary review of changes
3) Demonstration of change plan
4) The project management committee reviews
5) Issue change notice and organize implementation
6) Monitoring of change implementation
7) Evaluation of change effect
8) Judge whether the changed project has been put into the normal track
Four 、 Work content of project change management
Proposal of change 、 Treatment should be standardized , Especially when the overall pressure of the project is high . Batch processing can be used 、 Improve efficiency by prioritizing . If the project is small , The degree of association with other projects is small , The proposal and handling of changes can be handled simply and efficiently , But it still needs to be formal and standardized .
1、 Strictly control the submission of project change application
Strict control means , The change management system can ensure that the project benchmark can reflect the implementation of the project . All changes need to be submitted , But the efficiency can be improved according to the actual situation .
2、 Change control
1) Control of schedule change
Judge the current progress status , Control the factors that affect the progress , When progress changes , Manage it
2) Control of cost changes
Control the factors that affect the cost , Find out the cause of cost deviation , Managing change
3) Control of contract changes
Control contract modification
3、 The relationship between change management and other project management elements
1) Change management and overall management
Change management is a part of the overall project management .
2) Change management and configuration management
If the overall deliverables of the project are regarded as configuration items of the project , Change management can be seen as part of configuration management ;
Change management and configuration management can also be regarded as two sets of related mechanisms . When change comes , Configuration management invokes change management , Change management feeds the adjustment results back to configuration management .
5、 ... and 、 Version release and fallback plan
1、 Prepare before the software version is released
2、 Release the emergency fallback plan
3、 Summary of version release and rollback implementation process
In depth analysis of the reasons for fallback , To sum up your experience , Avoid fallback happening again ; Improve the fallback plan
边栏推荐
- 解决opencv在pycharm中代码提示失效
- 项目变更管理
- uni-app进阶之样式框架/生产环境【day10】
- Translation software Bob installation tutorial
- Matplotlib drawing and displaying Chinese
- jupyter-lab安装扩展后无法使用
- Operation and maintenance specification: process template for online fault handling
- postgres 通过 limit 切片数据
- Swiftui basic learning journal (XI) SQLite data operation
- 开发环境和测试环境的发包(及uniapp的request封装)
猜你喜欢

《MATLAB 神经网络43个案例分析》:第19章 基于SVM的手写字体识别

Analysis of 43 cases of MATLAB neural network: Chapter 9 associative memory of discrete Hopfield Neural Network -- number recognition

Matlab2020a how to export exe using app Designer

If you spend 200W to buy traffic, it is better to start at 0 cost and make an independent station with high private domain operation income!

Professional font design editor glyphs 3

Danfoss inverter maintenance vlt5000/vlt6000/vlt8000

Uniapp solves the cross domain problem of Google browser and runs in Google browser

有一说一,高并发系统设计其实一点都不难!

《MATLAB 神经网络43个案例分析》:第9章 离散Hopfield神经网络的联想记忆——数字识别
uni-app进阶之样式框架/生产环境【day10】
随机推荐
Readjustment of move protocol beta to expand the total prize pool
花200W买流量,不如0成本起步做独立站私域运营收益高!
Uniapp solves the cross domain problem of Google browser and runs in Google browser
mvn deploy多个模块的bat文件
Postgres slice data through limit
Parallel search exercise 1: circle of friends
Prediction of enzyme activity parameters by deep learning construction of enzyme binding model
WSL 2 installation process (and introduction)
[electronic scheme design] PCBA solution for alcohol tester
uniapp封装request函数 实现唯一登录,一个账号同时只能登陆一个设备
并查集练习题1:朋友圈
Move Protocol Beta测试版再调整,扩大总奖池
Speech breakpoint detection (short time improved subband spectral entropy)
Professional font design editor glyphs 3
Mongo uses too much memory and is automatically shut down by the system
uniapp在解决谷歌浏览器跨域问题,在谷歌浏览器运行
在小程序的 wxml 文件中使用 js 函数
在商业智能BI开发过程中,什么问题的挑战性最大?
Uni app advanced style framework / production environment [Day10]
深入浅出讲解 JS 的微任务与宏任务