Test Development Engineer Growth Diary 017 - The Life Cycle of a Bug
2022-07-30 07:41:00 【Octopus ball calf_】
Background:
During the previous project/iteration process, there were long bug fixes, untimely bug status, and doubts about how to transfer back to the testing process, which is not conducive to newcomers taking over the bug ticket processing.
Goal:
Clarify the specification of bug ticket circulation and bug handling time to reduce project risks caused by bug fixes.
Status flow:
Overall Status:

Instructions for filling in circulation:
1. Transfer to【Rejected】:
- A comment must be added to explain the specific situation; if a rejection statement/comment is missing, the bug ticket will be redirected to reopen
2. Transfer to [Resolved]:
- You can directly transfer from [Accepted] to [Resolved], skipping [Processed];
- The corresponding defect cause category must be selected;
- Comments must be added: add a summary description of the cause of the problem and the solution;
- For the front-end and back-end issues, when one side (front-end/back-end) finishes processing, the one that finishes first will actively confirm whether the other side has handled it.If the other party has processed it, it will be transferred after the verification is passed; if the other party has not completed the processing, the person can be removed from the processor, and the processor who has completed the process will transfer it separately;
3. Go to [Reopen]:
- A comment must be added to explain the latest verification results; R&D needs to pay attention to the comment information in this state in time
4. Transfer to 【Extension】:
- Need to pass the bug review meeting, initiate R&D, and reach agreement on production, R&D, and testing, and then transfer from unified testing to deferred and legacy pool iteration;
- In subsequent iterations, it is recommended that R&D arrange man-hours and fix no less than 30 bugs in the legacy pool every month; [Suggestion]
[Current Iteration] Repair Instructions:
1. [Test period] Bug day clearing rules:
Urgent bug:
- Repair and submit the code on the same day, and the test and verification pass until the bug ticket is closed;
High-quality bug:
- Submit before 16:00 on the same day, repair and submit on the same day, pass the test verification, until the bug ticket is closed;
- Submit after 16:00 on the same day, fix and submit before 12:00 noon the next day, complete the test verification before 16:00 the next day, until the bug ticket is closed;
Zhongyou bug:
- Fix and submit within 48 hours, the test and verification pass, until the bug ticket is closed;
Low-quality bug:
- According to the arrangement of R&D human resources, confirm whether to postpone the circulation in the follow-up bug review meeting;
- If there is no extension, it needs to be repaired or closed within one week;
- If it is postponed, it needs to be repaired or closed within one month;
2. [During the test period] Test verification bug:
- Complete before 20:00 every day, and close the verification of emergency bugs and high-quality bugs;
3. [Testing period] Statistics feedback of bug list that does not meet Nissin rules:
- We will count the daily results of Zhongyou bugs every week, and email synchronous development TL for feedback;
边栏推荐
猜你喜欢
随机推荐
图计算在网络安全分析中的应用
Unity Shader标准光照模型——高光反射
Ingress:从静态图分析到动态图分析
How to save modelsim simulation data as a file
flask项目快速搭建部署gunicorn+supervisor
OP 代币和不可转让的 NFT 致力于建立新的数字民主
大厂年薪50w+招聘具有测试平台开发能力的测试工程师
用于标记蛋白质和抗体的Biotin-LC-Sulfo-NHS|CAS:191671-46-2
网络协议01 - 基础概念
Unity Gizmos扩展:线框圆
05-Theos
JSP自定义标签
图扑数字孪生煤矿开采系统,打造采煤“硬实力”
kubernetes搭建SonarQube进行代码扫描
MongoDB-介绍,数据类型,基本语句
原力计划微服务实战|集中配置中心Config非对称加密与安全管理
ThreeJS导入外部obj和mtl
How to import matlab data into modelsim simulation
prometheus监控mysql
Biotin-NH2|CAS:111790-37-5(生物素-氨基)是一种生物素化化合物