Daily three questions 6.30
2022-07-01 23:20:00 【FightAlita】
0. A project is expected to bring... To a business unit 20% Increased profitability . In the closing process , The project manager found that the project realized 30% Profit growth of . A key stakeholder insisted on adding more functionality to the scope , To further improve profitability . What a project manager should do ?
A. Meet with this key stakeholder to understand the nature of these functions , And prepare scope change request for approval .
B. Discuss the matter with the key stakeholders and the project sponsor , If the sponsor approves , Then proceed with the change .
C. Prepare the final project report by ensuring that the expected deliverables in the project charter are consistent with the implemented projects , And communicate the report with the key interested party .
D. Arrange a meeting of all interested parties , The key interested party can propose scope changes in the conference room , And request the formal approval of other relevant parties .
analysis :B It's a reference answer
1、 A project has been subcontracted to a declared bankrupt supplier , The project manager follows the approved actions , But a project stakeholder questioned the appropriateness of the action . What documents should the project manager share with the project stakeholders ?
A. Risk register
B. Risk urgency assessment
C. The impact analysis
D. qualitative analysis
1. analysis :A It's a reference answer . Bankrupt suppliers still have production capacity , But it is likely to lose its vitality completely , It's the risk .
PM The approved actions followed should have been recorded in the risk register , It can be shown to the questionable stakeholders . Knowledge point :
chapter 11.2.3.1.
2、 At the risk assessment meeting of the project , The probability of occurrence of a risk item in the observation list increases sharply . What should the project manager update first ?
A. Risk management plan
B. Risk register
C. Hypothesis log
D. Risk response plan
2. analysis :B It's a reference answer . When the identified risks change, the risk register needs to be updated first . Knowledge point : chapter
11.2.3.1.
3、 After the project management plan is approved , The project manager is informed that there are potential problems in the working environment of the project . Which document should the project manager review ?
A. Project Charter
B. Quality management plan
C. Stakeholder management plan
D. Organizational process assets
3. analysis :D It's a reference answer . The test point of this question is 11.2 Input for identifying risks . The title stem said “ The work environment ” It's a
Interference point , The key word is “ The work environment ” Caused by the “ Potential problems ”, The potential problem is the risk of uncertainty ,B Options
and D Options are inputs for identifying risks , however D The options are more in line with the meaning of the question . in addition ,OPAs It could be a file ,
It may also be multiple files or knowledge bases .
边栏推荐
猜你喜欢

window10安装wsl(一)(WslRegisterDistribution ERROR)

The last packet sent successfully to the server was 0 milliseconds ago. The driver has not received

2022 crane driver (limited to bridge crane) examination questions and simulation examination

win 10 mstsc连接 RemoteApp

2022 R1 fast opening pressure vessel operation test questions and answers

Matplotlib常用设置
![[MySQL] basic use of explain and the function of each column](/img/d6/64f65ba21f5cda2c409477705f6a79.png)
[MySQL] basic use of explain and the function of each column

91. (cesium chapter) cesium rocket launch simulation

OpenVINO 模型性能评估工具—DL Workbench

Yoga27 multidimensional all-in-one computer with excellent appearance and high-end configuration
随机推荐
2022年起重机司机(限桥式起重机)考试试题及模拟考试
Jerry's question about long press boot detection [chapter]
flutter Unable to load asset: assets/images/888.png
想请教一下,证券开户选择哪个证券比较好?手机开户是安全么?
CADD course learning (3) -- target drug interaction
Zhongang Mining: it has inherent advantages to develop the characteristic chemical industry dominated by fluorine chemical industry
Timer和ScheduledThreadPoolExecutor的区别
众昂矿业:发展以氟化工为主的特色化工产业具有先天优势
2022 R1 fast opening pressure vessel operation test questions and answers
What is the relationship between modeling and later film and television?
window10安装wsl(一)(WslRegisterDistribution ERROR)
Matplotlib常用設置
2022年危险化学品经营单位安全管理人员考试题及在线模拟考试
2022 safety officer-c certificate examination question simulation examination question bank and simulation examination
vim给目录加颜色
Jielizhi, production line assembly link [chapter]
2022安全员-C证考试题模拟考试题库及模拟考试
Wechat personal small store one click opening assistant applet development
每日三题 6.28
2022 examination questions and online simulation examination for safety management personnel of hazardous chemical business units