PMP examination key summary VIII - monitoring process group (2)
2022-06-28 09:27:00 【The green flowers of Wang Li's family】
One 、 Control resources
Input :
1. Project management plan
① Resource management plan
2. Project documents
① Problem log
② Register of lessons learned
③ Physical resource allocation form
④ Project schedule
⑤ Resource breakdown structure
⑥ Resource requirements
⑦ Risk register
3. Performance data
4. agreement
5. Organizational process assets
Tools & technology
1. Data analysis
① Alternatives Analysis
② Cost benefit analysis
③ Performance review
④ Trend analysis
2. Problem solving —— Identify the problem 、 Define the problem 、 survey 、 analysis 、 solve 、 Check the solution .
3. Interpersonal and team skills
① negotiation
② influence
4. Project management information system
Output :
1. Job performance information
2. Change request
3. Project management plan update
① Resource management plan
② Progress benchmark
③ Cost basis
4. Project file update
① Hypothesis log
② Problem log
③ Register of lessons learned
④ Physical resource allocation form
⑤ Resource breakdown structure
⑥ Risk register
a key :
1、 Controlling resources means allocating physical resources .
Two 、 Monitoring communication
Input :
1. Project management plan
① Resource management plan
② Communication management plan
③ Participation plan of interested parties
2. Project documents
① Problem log
② Register of lessons learned
③ Project communication record
3. Performance data
4. Business environment factors
5. Organizational process assets
Tools & technology
1. Expert judgment
2. Project information management system
3. Data performance
① Stakeholder engagement assessment matrix
4. Interpersonal and team skills
① Observe / conversation
5. meeting
Output :
1. Job performance information
2. Change request
3. Project management plan update
① Communication management plan
② Participation plan of interested parties
4. Update project documents
① Problem log
② Register of lessons learned
③ Register of interested parties
3、 ... and 、 Monitoring risk
Input :
1. Project management plan
① Risk management plan
2. Project documents
① Problem log
② Register of lessons learned
③ Risk register
④ Risk Report
3. Performance data
4. Work performance report
Tools & technology
1. Data analysis
① Technical performance analysis
② Reserve analysis
2. Audit
3. meeting —— Regular risk reviews should be scheduled , To check and document the effectiveness of risk response in dealing with overall project risks and identified individual project risks . In the risk review , New individual project risks can also be identified ( Including secondary risks arising from agreed response measures ), Reassess current risks , Close obsolete risk .
Output :
1. Job performance information
2. Change request
3. Project management plan update
① Any component
4. Project file update
① Hypothesis log
② Problem log
③ Register of lessons learned
④ Risk register
⑤ Risk Report
5. Organizational process asset update
a key :
1、 Audit —— Risk audit is an audit type , It can be used to evaluate the effectiveness of the risk management process .
2、 A review conference : Regular risk reviews should be scheduled , To check and document the effectiveness of risk response in dealing with overall project risks and identified individual project risks . In the risk review , New individual project risks can also be identified ( Including secondary risks arising from agreed response measures ), Reassess current risks , Close obsolete risk .
3、 Contingency plan : Pre planned countermeasures .
4、 Contingency measures : There is a risk that has not been arranged , Urgent temporary measures .
Four 、 Control purchasing
Input :
1. Project management plan
① Demand management plan
② Risk management plan
③ Procurement management plan
④ Change management plan
⑤ Progress benchmark
2. Project documents
① Hypothesis log
② Register of lessons learned
③ Milestone List
④ Quality report
⑤ Requirements document
⑥ Demand tracking matrix
⑦ Risk register
⑧ Register of interested parties
3. agreement
4. Purchasing documents
5. Approved change request
6. Performance data
7. Business environment factors
8. Organizational process assets
Tools & technology
1. Expert judgment
2. Claim management
3. Data analysis
① Performance review
② Earned value analysis
③ Trend analysis
4. Check
5. Audit
Output :
1. Purchase closed
2. Job performance information
3. Purchasing document update
4. Change request
5. Project management plan update
① Risk management plan
② Procurement management plan
③ Progress benchmark
④ Cost basis
6. Project file update
① Register of lessons learned
② Resource requirements
③ Demand tracking matrix
④ Risk register
⑤ Register of interested parties
7. Organizational process asset update
a key :
1、 Claim management —— Negotiation is the preferred way to settle all claims and disputes .
2、 Check —— Inspection means a structured review of the work being performed by the contractor , It may involve a simple review of deliverables , Or field review of the work itself .
3、 Audit —— Audit is a structured review of the procurement process . The rights and obligations related to audit shall be clearly stipulated in the procurement contract .
4、 Purchase closed —— Requirements for formal closure of procurement , It is usually stipulated in the terms and conditions of the contract , And included in the procurement management plan .
5、 ... and 、 Monitor stakeholder engagement
Input :
1. Project management plan
① Resource management plan
② Communication management plan
③ Participation plan of interested parties
2. Project documents
① Problem log
② Register of lessons learned
③ Project communication record
④ Risk register
⑤ Register of interested parties
3. Performance data
4. Business environment factors
5. Organizational process assets
Tools & technology
1. Data analysis
① Alternatives Analysis
② Root cause analysis
③ Analysis of interested parties
① Multi criteria decision analysis
② vote
3. Data performance
① Stakeholder engagement assessment matrix
4. Communication skills
① feedback
② demonstration
5. Interpersonal and team skills
① Listen actively
② Cultural awareness
③ leadership
④ Interpersonal communication
⑤ political consciousness
6. meeting
Output :
1. Job performance information
2. Change request
3. Project management plan update
① Resource management plan
② Communication management plan
③ Participation plan of interested parties
4. Project file update
① Problem log
② Register of lessons learned
③ Risk register
④ Register of interested parties
6、 ... and 、 Scope of confirmation
Input :
1. Project management plan
① Scope management plan
② Demand management plan
③ Range reference
2. Project documents
① Register of lessons learned
② Quality report
③ Requirements document
④ Demand tracking matrix
3. Verified deliverables
4. Performance data
Tools & technology
1. Check
2. Decision making
① vote
Output :
1. Acceptable deliverables
2. Change request
3. Job performance information
4. Project file update
① Register of lessons learned
② Requirements document
③ Demand tracking matrix
a key :
1、 Acceptable deliverables —— Deliverables that meet the acceptance criteria shall be formally signed and approved by the customer or sponsor . Formal documentation should be obtained from the customer or sponsor , Prove the formal acceptance of project deliverables by relevant parties .
2、 The verified deliverable is the output of quality control .
7、 ... and 、 Monitor project work
Input :
1. Project management plan
2. Project documents
① Hypothesis log
② Estimation basis
③ Cost forecast
④ Problem log
⑤ Register of lessons learned
⑥ Milestone List
⑦ Quality report
⑧ Risk register
⑨ Risk Report
⑩ Progress forecast
3. Job performance information
4. agreement
5. Business environment factors
6. Organizational process assets
Tools & technology
1. Expert judgment
2. Data analysis
① Alternatives Analysis
② Cost benefit analysis
③ Earned value analysis
④ Root cause analysis
⑤ Trend analysis
⑥ Deviation analysis
3. Decision making
① vote
4. meeting
Output :
1. Work performance report —— It can be expressed as helping to attract attention 、 Decision making and action .
2. Change request
3. Project management plan update
4. Project file update
① Cost forecast
② Problem log
③ Register of lessons learned
④ Risk register
⑤ Progress forecast
8、 ... and 、 Implement overall change control
Input :
1. Project management plan
① Change management plan
② Configuration management plan
③ Range reference
④ Progress benchmark
⑤ Cost basis
2. Project documents
① Estimation basis
② Demand tracking matrix
③ Risk Report
3. Work performance report
4. Change request
5. Business environment factors
6. Organizational process assets
Tools & technology
1. Expert judgment
2. Change control tools —— Configuration identifier 、 Record and report configuration item status 、 Conduct Configuration Item Verification and audit .
3. Data analysis
① Alternatives Analysis
② Cost benefit analysis
4. Decision making
① vote .
② Authoritarian decision making
③ Multi criteria decision analysis
5. meeting
Output :
1. Approved change request
2. Project management plan update
3. Project file update
① Change log
a key :
1、 The project manager is ultimately responsible for this .
2、 The project manager approves minor changes ,CCB Approve changes involving benchmarks , The sponsor approves the change of the articles of association , The customer approves the relevant changes implemented according to the contract .
3、 The change process is as follows :
边栏推荐
猜你喜欢

Expérience d'optimisation SQL: de 30248 secondes à 0001 secondes

1. Kimball dimension modeling of data warehouse: what is a fact table?

Why does select * lead to low query efficiency?

Full link service tracking implementation scheme

A classic JVM class loaded interview question class singleton{static singleton instance = new singleton(); private singleton() {}

DEJA_ Vu3d - 051 of cesium function set - perfect realization of terrain excavation

Test cases for learning the basic content of software testing (II)

The Cassandra cluster reinstalls and starts from the node. An error is reported. There is an existing solution
理解IO模型

The concept of "tree structure" perfectly interprets the primary and secondary of things
随机推荐
new URL(“www.jjj.com“)
数字人行业爆发在即,市场格局几何?
4 methods for exception handling
SQL 优化经历:从 30248秒到 0.001秒的经历
Edit the live broadcast source code with me. How to write the live broadcast app code
==和eqauls()的区别
1180: fractional line delimitation /p1068 [noip2009 popularization group] fractional line delimitation
手机号、邮箱正则验证[通俗易懂]
Loggerfactory uses log4j Parameter introduction of properties
Data mining modeling practice
How to solve the problem of port number occupation
Learn how Alibaba manages the data indicator system
DolphinScheduler使用系统时间
小米旗下支付公司被罚 12 万,涉违规开立支付账户等:雷军为法定代表人,产品包括 MIUI 钱包 App
1182: effets de la photo de groupe
When the interviewer asks you to write binarysort in two ways
[ybtoj advanced training guidance] class roll call [string hash]
全局异常处理器与统一返回结果
学习阿里如何进行数据指标体系的治理
RMAN backup message ora-19809 ora-19804