当前位置:网站首页>Information System Project Manager Core Test Site (55) Configuration Manager (CMO) Work
Information System Project Manager Core Test Site (55) Configuration Manager (CMO) Work
2022-07-31 04:55:00 【qiangge2015】
Kekego brings you the work of the core key test site (55) configuration administrator (CMO) of the soft examination information system project manager, including mind map + real questions

[Information System Project Manager Core Test Site] Configuration Administrator (CMO) work
1. Develop a configuration management plan
2. Identify configuration items, establish configuration library and baseline
3. Incorporate the changed configuration into the baseline, and notify relevant personnel of the changes and results
4. Version management and configuration control
5. Configuration audit, configuration management training, etc.
6. Strictly manage the operation authority of all configuration items [P473-P474]
【Mind Map of Core Test Centers】

[Core test center real questions]
1. In order to manage the project configuration, a system integration enterprise defines the operation authority in the configuration library as follows:

At the same time, the operation permissions of the project-related personnel in the development library are assigned as follows, where J indicates that the person has the corresponding authority, and X indicates that the person does not have the corresponding authority.

The position marked with ①②③④⑤ in the development library permission allocation table should be filled in:( )
A, ①√, ②×, ③×, ④√, ⑤√
B, ①√, ②√, ③√, ④×, ⑤√
C. ①√, ②√, ③×, ④×, ⑤√
D, ①×, ②√, ③√, ④×, ⑥×
【Answer】B
[Analysis] Advanced Textbook Second Edition P325: The configuration administrator assigns each project member the operation authority to the configuration library.Generally, project members have the permissions of Add, Checkin/Checkout, Download, etc., but cannot have the "Delete" permission.The configuration administrator has the highest authority.The specific operation depends on the configuration management software used.
With this and actual experience, it can be known that: ①The project manager should have the Check authority of the document; ②The QA is the quality management personnel, and can have the Add authority of the document (such as adding quality documents, etc.); ③The project member of the middleThere should be the Check permission of the code; ④ The tester must not have the permission to add the code; ⑤ The configuration administrator has all the permissions, so it should also be ticked.So the answer is B.
2. In configuration management, the configuration repository used to manage the current baseline and control changes to the baseline is ( )
A, dynamic library B, backup library C, controlled library D, static library
【Answer】C
[Analysis] Development library (dynamic library): Stores various information that needs to be retained during the development process.
Controlled library (main library): Stores the results of a certain stage, and the reading, writing and modification of information in the library are limited.A configuration repository for managing current baselines and controlling changes to baselines
Product Libraries (Static Libraries): Form final products, awaiting delivery or field installation.The information in the library is strictly limited.
Backup library: backup of important configuration information, restore damaged configuration library data in emergency.
3. Regarding the formulation and approval of the configuration management plan, the following statement is correct ( )
A. The configuration management plan should be formulated by the configuration management personnel and approved by the project manager
B. The configuration management plan should be formulated by the project manager and approved by the configuration control committee
C. The configuration management plan should be formulated by the project manager and approved by the personnel
D. The configuration management plan should be formulated by the configuration management personnel and approved by the configuration control committee
【Answer】D
[Analysis] P319 of the second edition of the advanced textbook, the 8th line from the bottom.The configuration management plan should be approved by the Configuration Control Board, with answers B and D locked first.The configuration management plan should of course be developed by the configuration manager, not the project manager.So answer D is correct.
4. The project team implements role-based access control to an important resource.The project manager ((PM) is the system administrator. The project member roles also include configuration administrators ((CM), analysts, designers, developers, and quality assurance personnel (QA), where CM and QA are involved in multiple projects at the same time.Which of the following statements about the assignment of access rights to this resource is true ( ).
A. CM access should be assigned by PM and should be approved by QA.
B. QA's access rights should be assigned by the PM and should be transferred to the CM when they are not involved in the project
Access for C, Analyst, Designer, Developer should be assigned by CM and approved by QA
D, PM's access rights are assigned by themselves, and their rights cannot be transferred to QA and CM when PM is away
【Answer】D
【Analysis】
Answer A: The CM is the configuration administrator and should have the highest (or most) authority. After the PM is assigned, there is no need for QA to approve it.So A is wrong.
Answer B: The authority of QA cannot and does not need to be transferred to CM.wrong.See the third line of P616 of the second edition of the advanced textbook, role-based access control: users can not voluntarily pass access rights to others, which is a non-voluntary access control.
Answer C: It says that the project manager is the system administrator, so access rights should be assigned by the project manager, not the CM.
Answer D: Correct, PM is the system administrator, so its anti-question authority is assigned by itself, and the authority of the system administrator cannot be transferred to QA and CM.
To sum up, the answer is D, which is based on the rules of role-based access control.There are also reference answers that think it is C, and the reason refers to P325 of the second edition of the advanced textbook: Configuration administrators assign operation permissions to the configuration library for each project member.Generally, project members have the permissions of Add, Checkin/Checkout, Download, etc., but cannot have the "Delete" permission.The configuration administrator has the highest authority.I think that CM has the highest authority, so it is C, but this does not meet the requirements of the question.So the recommended answer is D.
边栏推荐
- PCL 计算点云坐标最值及其索引
- [C language] Detailed explanation of operators
- 【wpf】wpf中的那些模板之深度解析
- npm、nrm两种方式查看源和切换镜像
- 【线性神经网络】softmax回归
- STM32——DMA
- Solved (the latest version of selenium framework element positioning error) NameError: name 'By' is not defined
- 110道 MySQL面试题及答案 (持续更新)
- Error EPERM operation not permitted, mkdir 'Dsoftwarenodejsnode_cache_cacach Two solutions
- PWN ROP
猜你喜欢

ENSP, VLAN division, static routing, comprehensive configuration of Layer 3 switches

Mysql应用安装后找不到my.ini文件

ERROR 1064 (42000) You have an error in your SQL syntax; check the manual that corresponds to your

论治理与创新 | 2022开放原子全球开源峰会OpenAnolis分论坛圆满召开

sql statement - how to query data in another table based on the data in one table

XSS shooting range (3) prompt to win

View source and switch mirrors in two ways: npm and nrm

Unity教程:URP渲染管线实战教程系列【1】

ERROR 2003 (HY000) Can't connect to MySQL server on 'localhost3306' (10061)Solution

MySQL database addition, deletion, modification and query (detailed explanation of basic operation commands)
随机推荐
SOLVED: After accidentally uninstalling pip (two ways to manually install pip)
WeChat applet uses cloud functions to update and add cloud database nested array elements
Centos7 install mysql5.7 steps (graphical version)
12 reasons for MySQL slow query
打造基于ILRuntime热更新的组件化开发
The MySQL database installed configuration nanny level tutorial for 8.0.29 (for example) have hands
从零开始,一镜到底,纯净系统搭建除草机(Grasscutter)
DVWA安装教程(懂你的不懂·详细)
On Governance and Innovation | 2022 OpenAtom Global Open Source Summit OpenAnolis sub-forum was successfully held
STM32——DMA
unity2d game
MySQL window function
Unity Tutorial: URP Rendering Pipeline Practical Tutorial Series [1]
Go language study notes - dealing with timeout problems - Context usage | Go language from scratch
XSS shooting range (3) prompt to win
关于出现大量close_wait状态的理解
centos7安装mysql5.7
开源汇智创未来 | 2022开放原子全球开源峰会OpenAtom openEuler分论坛圆满召开
DVWA靶场环境搭建
open failed: EACCES (Permission denied)