Key summary V of PMP examination - execution process group
2022-06-28 09:27:00 【The green flowers of Wang Li's family】
One 、 Integrated management
( One ) Guide and manage project work
Input :
1. Project management plan
2. Project documents
① Change log
② Register of lessons learned
③ Milestone List
④ Project communication record
⑤ Project schedule
⑥ Demand tracking matrix
⑦ Risk register
⑧ Risk Report
3. Approved change request
4. Business environment factors
5. Organizational process assets
Tools & technology
1. Expert judgment
2. Project management information system —— Including the software tools for schedule planning 、 Work authorization system 、 Configuration management system 、 Information collection and distribution system , Automatic collection and reporting
Report key performance indicators (KPI)
3. meeting
Output :
1. Deliverables
2. Performance data
3. Problem log
4. Change request
5. Project management plan update
6. Project file update
① Activity list
② Hypothesis log
③ Register of lessons learned
④ Requirements document
⑤ Risk register
⑥ Register of interested parties
7. Organizational process asset update
a key :
1、 Change request —— Corrective actions 、 Preventive measures 、 Defect remedy 、 to update .
( Two ) Manage project knowledge
Input :
1. Project management plan
2. Project documents
① Register of lessons learned
② Project team dispatch list
③ Resource breakdown structure
④ Register of interested parties
3. Deliverables
4. Business environment factors
5. Organizational process assets
Tools & technology
1. Expert judgment
2. knowledge management
3. information management
4. Interpersonal and team skills
① Listen actively
② guide
③ leadership
④ Interpersonal communication
⑤ political consciousness
Output :
1. Register of lessons learned
2. Project management plan update
3. Organizational process asset update
a key :
1、 Explicit knowledge and tacit knowledge ;
2、 The lessons learned register contains both successful and failed lessons , Can be created early in the project .
Two 、 Management quality
( One ) Management quality
Input :
1. Project management plan
① Quality management plan
2. Project documents
① Register of lessons learned
② Quality control measurement results
③ Quality measurement index
④ Risk Report
3. Organizational process assets
Tools & technology
1. Data collection
① Checklist
2. Data analysis
① Alternatives Analysis
② File analysis
③ process analysis
④ Root cause analysis
3. Decision making
① Multi criteria decision analysis
4. Data performance
① Affinity graph
② Cause and effect diagram
③ flow chart
④ Histogram
⑤ Matrix diagram
⑥ Scatter plot
5. Audit
6. oriented X The design of the
7. Problem solving
8. Quality improvement methods —— plan — The implementation of — Check — Action and six sigma
Output :
1. Quality report
2. Test and evaluation documents
3. Change request
4. Project management plan update
① Quality management plan
② Range reference
③ Progress benchmark
④ Cost basis
5. Project file update
① Problem log
② Register of lessons learned
③ Risk register
a key :
1、 The experimental design provides a statistical framework for changing all factors of the system ;
2、 process analysis —— Process analysis can identify process improvement opportunities , Also check the problems encountered during the process 、 Constraints , And non value-added activities .
3、 Root cause analysis —— The root cause analysis is to determine the cause of the deviation 、 An analytical technique for the root cause of a defect or risk .
4、① Affinity graph —— Affinity maps can be used to classify the causes of potential defects , Show what you should focus on most .
② Cause and effect diagram —— also called “ fishbone diagram ”、“why-why Analysis chart ” and “ Ishikawa ”, Decompose the cause of the problem statement into discrete branches , Helps identify the main or root cause of the problem .
③ flow chart —— The flow chart shows a series of steps to cause a defect .
④ Histogram —— A histogram is a bar graph showing digital data .
⑤ Matrix diagram —— The matrix shows the factors where the rows and columns intersect 、 The strength of the relationship between cause and goal .
⑥ Scatter plot —— A scatter chart is a graph that shows the relationship between two variables .
5、 Problem solving process :
Define the problem ; Identify root cause ; Build possible solutions ; Choose the best solution ; Execute solution ; Validate the solution .
6、 Quality audit : Audit is used to determine whether the project activities comply with the policies of the organization and the project 、 A structured and independent process of a program .
7、 oriented X The design of the —— To optimize specific aspects of the design , It can control or improve the final characteristics of the product .
3、 ... and 、 Management resources
( One ) Access to resources
Input :
1. Project management plan
① Resource management plan
② Procurement management plan
③ Cost basis
2. Project documents
① Project schedule
② Resource Calendar
③ Resource requirements
④ Register of interested parties
3. Business environment factors
4. Organizational process assets
Tools & technology
1. Decision making —— Usability 、 cost 、 Ability 、 Experience 、 knowledge 、 Skill 、 attitude 、 The international factors
① Multi criteria decision analysis
2. Interpersonal and team skills
① negotiation
3. Pre-assignment
4. Virtual team
Output :
1. Physical resource allocation form —— The physical resource allocation sheet records the materials to be used in the project 、 equipment 、 Articles 、 Location and other physical resources .
2. Project team dispatch list —— The project team dispatch list records the team members and their roles and responsibilities in the project .
3. Resource Calendar
4. Change request
5. Project management plan update
① Resource management plan
② Cost basis
6. Project file update
① Register of lessons learned
② Project schedule
③ Resource breakdown structure
④ Resource requirements
⑤ Risk register
⑥ Register of interested parties
7. Renewal of business environment factors
8. Organizational process asset update
a key :
1、 Pre-assignment —— Pre assignment refers to the prior determination of the physical or team resources of the project .
2、 Virtual team —— Virtual teams can be defined as having common goals 、 A group of people who have little or no time to work face-to-face in completing their role tasks .
3、 The resource calendar indicates a detailed calendar of working and non working days for each specific resource .
( Two ) Build the team
Input :
1. Project management plan
① Resource management plan
2. Project documents
① Register of lessons learned
② Project schedule
③ Project team dispatch list
④ Resource Calendar
⑤ Team Charter
3. Business environment factors —— Human resource management policies for hiring and firing 、 Employee performance review 、 Employee development and training records , And recognition and reward
4. Organizational process assets
Tools & technology
1. Centralized office
2. Virtual team
3. Communication technology
4. Interpersonal and team skills
① conflict management
② influence
③ incentive
④ negotiation
⑤ Team building
5. Recognition and reward —— Only rewards that meet an important need of the rewarded person , Is an effective reward .
6. train
7. Individual and team assessment
8. meeting
Output :
1. Team performance evaluation
2. Change request
3. Project management plan update
① Resource management plan
4. Project file update
① Register of lessons learned
② Project schedule
③ Project team dispatch list
④ Resource Calendar
⑤ Team Charter
5. Renewal of business environment factors
6. Organizational process asset update
a key :
1、 Team building is to improve project performance .
2、 Centralized office —— Centralized office means that many or all of the most active project team members are arranged to work in the same physical location , To enhance team work ability .
3、 Team performance evaluation —— Improvement of personal skills 、 Improvement of team ability 、 Reduction of turnover rate of team members 、 Strengthen team cohesion .
4、 Training is important .
( 3、 ... and ) Management team
Input :
1. Project management plan
① Resource management plan
2. Project documents
① Problem log
② Register of lessons learned
③ Project team dispatch list
④ Team Charter
3. Work performance report
4. Team performance evaluation
5. Business environment factors
6. Organizational process assets
Tools & technology
1. Interpersonal and team skills
① conflict management
② Making decisions —— Decision making includes the ability to negotiate and influence the organization and project management team .
③ EQ —— EQ refers to identification 、 Evaluate and manage personal emotions 、 The ability of others' emotions and group emotions .
④ influence
⑤ leadership —— Leadership is very important for communicating the vision and encouraging the project team to work efficiently .
2. Project management information system
Output :
1. Change request
2. Project management plan update
① Resource management plan
② Progress benchmark
③ Cost basis
3. Project file update
① Problem log
② Register of lessons learned
③ Project team dispatch list
4. Renewal of business environment factors
a key :
1、 conflict management —— retreat / avoid 、 to moderate / inclusive 、 compromise / Mediation 、 Force / command 、 cooperation / solve the problem . Here's the picture :
Four 、 Management communication
( One ) Communication management
Input :
1. Project management plan
① Resource management plan
② Communication management plan
③ Participation plan of interested parties
2. Project documents
① Change log
② Problem log
③ Register of lessons learned
④ Quality report
⑤ Risk Report
⑥ Register of interested parties
3. Work performance report —— Typical examples of job performance reports include status reports and progress reports .
4. Business environment factors
5. Organizational process assets
Tools & technology
1. Communication technology
2. Communication methods
3. Communication skills
① Communication competence
② feedback
③ Nonverbal
④ demonstration
4. Project management information system
5. Project report release
6. Interpersonal and team skills
① Listen actively
② conflict management
③ Cultural awareness
④ Conference Management
⑤ Interpersonal communication
⑥ political consciousness
7. meeting
Output :
1. Project communication record
2. Project management plan update
① Communication management plan
② Participation plan of interested parties
3. Project file update
① Problem log
② Register of lessons learned
③ Project schedule
④ Risk register
⑤ Register of interested parties
4. Organizational process asset update
a key :
1、 Project report release —— Project report publishing is the act of collecting and publishing project information . Project information should be released to a large number of interested parties . The appropriate level of project information release shall be adjusted for each interested party 、 Form and details .
5、 ... and 、 To manage risk
( One ) Implement risk response
Input :
1. Project management plan
① Risk management plan
2. Project documents
① Register of lessons learned
② Risk register
③ Risk Report
3. Organizational process assets
Tools & technology
1. Expert judgment
2. Interpersonal and team skills
① influence —— Some risk response measures may be implemented by personnel outside the immediate project team , Or by people with other competitive needs . In this case , Project managers or personnel responsible for guiding the risk management process need to exert their influence .
3. Project management information system
Output :
1. Change request
2. Project file update
① Problem log
② Register of lessons learned
③ Project team dispatch list
④ Risk register
⑤ Risk Report
a key :
1、 The risk owner is very important , The risk owner tries to implement the countermeasures , To actively manage risks .
6、 ... and 、 Manage purchasing
( One ) Implement procurement
Input :
1. Project management plan
① Scope management plan
② Demand management plan
③ Communication management plan
④ Risk management plan
⑤ Configuration management plan
⑥ Cost basis
2. Project documents
① Register of lessons learned
② Project schedule
③ Requirements document
④ Risk register
⑤ Register of interested parties
3. Purchasing documents —— Bidding documents 、 Purchase statement of work 、 Independent cost estimation 、 Supplier selection criteria
4. Seller's proposal
5. Business environment factors
6. Organizational process assets
Tools & technology
1. Expert judgment
2. advertisement —— It is often possible to expand the existing list of potential sellers .
3. Bidder's meeting
4. Data analysis
① Proposal evaluation
5. Interpersonal and team skills
① negotiation
Output :
1. Selected seller
2. agreement —— Procurement statement of work or major deliverables ; Termination clauses and alternative dispute resolution methods, etc .
3. Change request
4. Project management plan update
① Demand management plan
② Quality management plan
③ Communication management plan
④ Risk management plan
⑤ Procurement management plan
⑥ Range reference
⑦ Progress benchmark
⑧ Cost basis
5. Project file update
① Register of lessons learned
② Requirements document
③ Demand tracking matrix
④ Resource Calendar
⑤ Risk register
⑥ Register of interested parties
6. Organizational process asset update
a key :
1、 Purchasing mainly involves selecting suppliers and signing agreements .
2、 Bidder's meeting —— The purpose is to ensure that all potential bidders have a clear and consistent understanding of the procurement requirements , And ensure that no bidder will receive special preferential treatment .
3、 The purchase statement of work will eventually become part of the agreement .
4、 negotiation —— The final wording of the document should reflect all the agreements reached by both parties . The negotiation shall be concluded by signing the contract documents or other formal agreements that can be executed by the buyer and the seller . The negotiation shall be led by the members of the procurement team who have the authority to sign the contract . The project manager and other members of the project management team can participate in the negotiation and provide necessary assistance .
7、 ... and 、 Managing stakeholders
( One ) Managing stakeholder engagement
Input :
1. Project management plan
① Communication management plan
② Risk management plan
③ Participation plan of interested parties
④ Change management plan
2. Project documents
① Change log
② Problem log
③ Register of lessons learned
④ Register of interested parties
3. Business environment factors
4. Organizational process assets
Tools & technology
1. Expert judgment
2. Communication skills
3. Interpersonal and team skills
① conflict management
② Cultural awareness
③ negotiation
④ Observe / conversation
⑤ political consciousness
4. The basic rule
5. meeting
Output :
1. Change request
2. Project management plan update
① Communication management plan
② Participation plan of interested parties
3. Project file update
① Change log
② Problem log
③ Register of lessons learned
④ Register of interested parties
a key :
1、 Managing stakeholder engagement is about increasing support , The process of reducing objections .
边栏推荐
- Music website design based on harmonyos (portal page)
- How to solve the problem of port number occupation
- English translation plug-in installation of idea
- 线程和进程
- PMP needs to master its own learning methods
- For the development of short video app, the elder warned me to choose the open source code
- Deployment of MySQL database in Linux Environment
- Data visualization makes correlation analysis easier to use
- rman備份報ORA-19809 ORA-19804
- How to reduce the risk of project communication?
猜你喜欢
随机推荐
Screen settings in the source code of OBS Live Room
Data visualization makes correlation analysis easier to use
自定义异常类及练习
1180:分数线划定/P1068 [NOIP2009 普及组] 分数线划定
SQL injection file read / write
异常处理4种方法
Postman interface test
"Jianzhi offer" -- Interview Question 4: finding two-dimensional arrays
线程和进程
异常的产生,及解决
Basic knowledge of hard disk (head, track, sector, cylinder)
如何实现基于 RADIUS 协议的双因子认证 MFA?
Understanding the IO model
Divide and rule classic Hanoi
new URL(“www.jjj.com“)
Summary of PMP learning experience
Scenario method and error recommendation method for learning basic content of software testing (2)
手机号、邮箱正则验证[通俗易懂]
The concept of "tree structure" perfectly interprets the primary and secondary of things
PMP考试重点总结七——监控过程组(1)