1. Type of change request
Including corrective measures 、 Preventive measures 、 Defect remedy and update
3、 A new government regulation will require changes to a product in the development stage . The project team revises the project management plan at the beginning of the project to implement new requirements , Instead of adding requirements later . What type of change request should be used ?( )
A. Corrective actions
B. Proactive measures
C. Preventive measures
D. to update
answer :D
analysis : This question examines the knowledge points : Type of change request .
This is the key to the problem : Revise the project management plan . Update refers to the change of formally controlled project documents or plans , To reflect modified or added comments or contents . The new government regulations in the title stem require changes , Conform to the updated concept , So choose D.
A Corrective measures are purposeful activities to make the project work performance consistent with the project management plan again .
B The types of change requests include corrective actions 、 Preventive measures 、 Defect remedy and update , There is no initiative .
C Preventive measures are purposeful activities to ensure that the future performance of the project work conforms to the project management plan .
2. Register of interested parties
The register of interested parties is “13.1 Identify interested parties ” Output file for , Record information about identified parties . The content includes
1、 Identity information . full name 、 Organizational position 、 place 、 Contact information , And their role in the project .
2、 Evaluation information . Main needs 、 expect 、 The potential to influence project outcomes , And the stage of the project life cycle that stakeholders can most influence or impact .
3、 Classification of related parties . Use internal or external , effect 、 influence 、 Power or interest , The superior 、 subordinate 、 Peripheral or lateral , Or other classification model chosen by the project manager , The result of classification .
PMP In the exam , Need to be clear : Contents of the register of interested parties ; Register of interested parties and participation plan of interested parties 、 The difference between communication management plans . The key points of the answer are as follows :
1、 First, clarify the interested parties , Refers to those organizations related to the project 、 personal . such as : The management of the company 、 Customer 、 Regulator 、 Functional departments, etc . Generally, the team is not included , Team is resource management ;
2、 After identifying new interested parties , Or when the interested parties change , Update the register of interested parties ;
3、 Want to know which parties are involved and their needs , see 《 Register of interested parties 》; Want to know how to manage interested parties and their participation , see 《 Participation plan of interested parties 》; How to exchange information with interested parties , yes 《 Communication management plan 》.
边栏推荐
- There is no one of the necessary magic skills PXE for old drivers to install!!!
- CAD插件的安装和自动加载dll、arx
- Method of finding prime number
- 1. 两数之和
- Skywalking8.7 source code analysis (I): agent startup process, agent configuration loading process, custom class loader agentclassloader, plug-in definition system, plug-in loading
- 多线程与高并发(7)——从ReentrantLock到AQS源码(两万字大章,一篇理解AQS)
- Strategy pattern: encapsulate changes and respond flexibly to changes in requirements
- [Shangshui Shuo series together] day 10
- 1. Sum of two numbers
- Apple submitted the new MAC model to the regulatory database before the spring conference
猜你喜欢

Convolution operation in convolution neural network CNN

Why is the website slow to open?

理解 期望(均值/估计值)和方差

Cesium 点击获取模型表面经纬度高程坐标(三维坐标)

arcgis创建postgre企业级数据库

Clickhouse learning notes (2): execution plan, table creation optimization, syntax optimization rules, query optimization, data consistency

Understand expectations (mean / estimate) and variances

Redhat7 system root user password cracking

Jedis source code analysis (II): jediscluster module source code analysis

Multithreading and high concurrency (7) -- from reentrantlock to AQS source code (20000 words, one understanding AQS)
随机推荐
[together Shangshui Shuo series] day 7 content +day8
最大似然估计,散度,交叉熵
Cesium 点击获三维坐标(经纬度高程)
Kubernetes notes (IX) kubernetes application encapsulation and expansion
Why is the website slow to open?
Error 1045 (28000) occurs when Linux logs in MySQL: access denied for user 'root' @ 'localhost' (using password: yes)
[teacher Zhao Yuqiang] calculate aggregation using MapReduce in mongodb
[teacher Zhao Yuqiang] index in mongodb (Part 2)
[trivia of two-dimensional array application] | [simple version] [detailed steps + code]
BeanDefinitionRegistryPostProcessor
Method of converting GPS coordinates to Baidu map coordinates
[function explanation (Part 1)] | | knowledge sorting + code analysis + graphic interpretation
How to create your own repository for software packages on Debian
Understand expectations (mean / estimate) and variances
Jackson: what if there is a lack of property- Jackson: What happens if a property is missing?
[set theory] relational closure (reflexive closure | symmetric closure | transitive closure)
Solve the problem that Anaconda environment cannot be accessed in PowerShell
pytorch 多分类中的损失函数
@Import annotation: four ways to import configuration classes & source code analysis
How does win7 solve the problem that telnet is not an internal or external command