1. Type of change request
Including corrective measures 、 Preventive measures 、 Defect remedy and update
3、 A new government regulation will require changes to a product in the development stage . The project team revises the project management plan at the beginning of the project to implement new requirements , Instead of adding requirements later . What type of change request should be used ?( )
A. Corrective actions
B. Proactive measures
C. Preventive measures
D. to update
answer :D
analysis : This question examines the knowledge points : Type of change request .
This is the key to the problem : Revise the project management plan . Update refers to the change of formally controlled project documents or plans , To reflect modified or added comments or contents . The new government regulations in the title stem require changes , Conform to the updated concept , So choose D.
A Corrective measures are purposeful activities to make the project work performance consistent with the project management plan again .
B The types of change requests include corrective actions 、 Preventive measures 、 Defect remedy and update , There is no initiative .
C Preventive measures are purposeful activities to ensure that the future performance of the project work conforms to the project management plan .
2. Register of interested parties
The register of interested parties is “13.1 Identify interested parties ” Output file for , Record information about identified parties . The content includes
1、 Identity information . full name 、 Organizational position 、 place 、 Contact information , And their role in the project .
2、 Evaluation information . Main needs 、 expect 、 The potential to influence project outcomes , And the stage of the project life cycle that stakeholders can most influence or impact .
3、 Classification of related parties . Use internal or external , effect 、 influence 、 Power or interest , The superior 、 subordinate 、 Peripheral or lateral , Or other classification model chosen by the project manager , The result of classification .
PMP In the exam , Need to be clear : Contents of the register of interested parties ; Register of interested parties and participation plan of interested parties 、 The difference between communication management plans . The key points of the answer are as follows :
1、 First, clarify the interested parties , Refers to those organizations related to the project 、 personal . such as : The management of the company 、 Customer 、 Regulator 、 Functional departments, etc . Generally, the team is not included , Team is resource management ;
2、 After identifying new interested parties , Or when the interested parties change , Update the register of interested parties ;
3、 Want to know which parties are involved and their needs , see 《 Register of interested parties 》; Want to know how to manage interested parties and their participation , see 《 Participation plan of interested parties 》; How to exchange information with interested parties , yes 《 Communication management plan 》.
边栏推荐
- 智牛股--03
- [function explanation (Part 2)] | [function declaration and definition + function recursion] key analysis + code diagram
- [Zhao Yuqiang] deploy kubernetes cluster with binary package
- Disruptor learning notes: basic use, core concepts and principles
- Leetcode problem solving summary, constantly updating!
- @Import annotation: four ways to import configuration classes & source code analysis
- Cesium 点击获三维坐标(经纬度高程)
- Understand the first prediction stage of yolov1
- MySQL 5.7.32-winx64 installation tutorial (support installing multiple MySQL services on one host)
- [teacher Zhao Yuqiang] index in mongodb (Part 2)
猜你喜欢

Kubernetes notes (VII) kuberetes scheduling

Method of converting GPS coordinates to Baidu map coordinates
![[escape character] [full of dry goods] super detailed explanation + code illustration!](/img/33/ec5a5e11bfd43f53f2767a9a0f0cc9.jpg)
[escape character] [full of dry goods] super detailed explanation + code illustration!

Kubernetes cluster environment construction & Deployment dashboard

SVN分支管理

Cesium 点击获三维坐标(经纬度高程)
![[teacher Zhao Yuqiang] index in mongodb (Part 1)](/img/2d/277ec737f2a7065831a19d036e61e1.jpg)
[teacher Zhao Yuqiang] index in mongodb (Part 1)

Oauth2.0 - using JWT to replace token and JWT content enhancement

Kubernetes notes (IX) kubernetes application encapsulation and expansion

Code generator - single table query crud - generator
随机推荐
[function explanation (Part 2)] | [function declaration and definition + function recursion] key analysis + code diagram
卷积神经网络CNN中的卷积操作详解
Synthetic keyword and NBAC mechanism
Bio, NiO, AIO details
Clickhouse learning notes (I): Clickhouse installation, data type, table engine, SQL operation
为什么网站打开速度慢?
[explain in depth the creation and destruction of function stack frames] | detailed analysis + graphic analysis
Jedis source code analysis (II): jediscluster module source code analysis
Kubernetes resource object introduction and common commands (V) - (configmap)
The server data is all gone! Thinking caused by a RAID5 crash
深度学习,从一维特性输入到多维特征输入引发的思考
[teacher Zhao Yuqiang] Alibaba cloud big data ACP certified Alibaba big data product system
MySQL 5.7.32-winx64 installation tutorial (support installing multiple MySQL services on one host)
@Import annotation: four ways to import configuration classes & source code analysis
[teacher Zhao Yuqiang] use Oracle's tracking file
Kubernetes notes (II) pod usage notes
Kubesphere - Multi tenant management
Convolution operation in convolution neural network CNN
Kubernetes notes (VII) kuberetes scheduling
Mysql database table export and import with binary