Preparations before upgrading
l Prepare the software version file required for the upgrade S5820V2_5830V2-CMW710-R2208P01.ipe;
l adopt ftp or tftp Upload the version file to slot1 and slot2 Of flash:/ Under the table of contents ;
1.1. Upgrade first Master equipment , Upgrade again Slave step
step
Job content
1
First delete the configuration about mad Detected configuration
[ASW-T06-I03.CM3]interface Bridge-Aggregation 100
[ASW-T06-I03.CM3-Bridge-Aggregation100]undo mad enable
2
take slot 1 All service ports in the device shutdown, And save the configuration
[ASW-T06-I03.CM3]interface range Ten-GigabitEthernet 1/0/1 to Ten-GigabitEthernet 1/0/48
[ASW-T06-I03.CM3-if-range]shutdown
<ASW-T06-I03.CM3>save
The current configuration will be written to the device. Are you sure? [Y/N]:y
Please input the file name(*.cfg)[flash:/config.cfg]
(To leave the existing filename unchanged, press the enter key):
flash:/config.cfg exists, overwrite? [Y/N]:y
Validating file. Please wait…
Saved the current configuration to mainboard device successfully.
Slot 2:
Save next configuration file successfully.
3
Appoint boot-loader, Restart upgrade slot1 Equipment to R2208P01 edition ; Restart the slot 1 Pass immediately after Slot2 Of Console mouth , stay Slot 2 On the device shutdown all IRF port .
<ASW-T06-I03.CM3>boot-loader file flash:/S5820V2_5830V2-CMW710-R2208P01.ipe slot 1 main
<ASW-T06-I03.CM3>reboot slot 1
Start to check configuration with next startup configuration file, please wait…DONE!
This command will reboot the specified slot, Continue? [Y/N]:y
Now rebooting, please wait…
%Jan 3 04:00:55:522 2011 ASW-T06-I03.CM3 DEV/5/BOARD_REBOOT: Board is rebooting on Slot 1.
<ASW-T06-I03.CM3>sys
[ASW-T06-I03.CM3] interface range FortyGigE 2/0/49 to FortyGigE 2/0/52
[ASW-T06-I03.CM3-if-range]shutdown
Be careful :
1、 Never reboot Wrong slot number ,slot 1! Remember !
Need to pass console Connect to Slot 2 On ,shutdown IRF port , This operation requires fast ,reboot Immediately after .
4
Console Connect to Slot 1 On the device , Upgrade the completed Slot 1 All the service ports in the device undo shutdown open .
[ASW-T06-I03.CM3]interface range Ten-GigabitEthernet 1/0/1 to Ten-GigabitEtherne
t 1/0/48
[ASW-T06-I03.CM3-if-range]undo shutdown
Be careful :
Do not save the configuration here !
5
Console Connect to Slot 2 On the device , Specify the startup file as R2208P01, restart slot 2 Upgraded version ;、
<ASW-T06-I03.CM3>boot-loader file flash:/S5820V2_5830V2-CMW710-R2208P01.ipe slot 2 main
<ASW-T06-I03.CM3>reboot slot 2
Start to check configuration with next startup configuration file, please wait…DONE!
Current configuration may be lost after the reboot, save current configuration? [Y/N]:N
This command will reboot the specified slot, Continue? [Y/N]:Y
Be careful :
Whether to save the configuration pops up here , Be sure to choose N
6
Check whether the stack is successful , Whether the aggregation group status is normal , Whether the configuration is complete
7
Restore previously deleted mad Detected configuration , And save the configuration .
[ASW-T06-I03.CM3]interface Bridge-Aggregation 100
[ASW-T06-I03.CM3-Bridge-Aggregation100] mad enable
1、 The configuration will not be lost after upgrading ;
2、 During the upgrade , In addition to 2、7 Step , There is no need to save the configuration in other steps ;
3、 Intermediate state of upgrade , The versions of the two devices are inconsistent , When all service ports are opened , because IRF Split the rear axle MAC The address is the same , therefore LACP Neighbors and these two S58V2 Two devices cannot be distinguished when connected , The port status will be set to Select state ;
4、 Upgrade to R2208P01 Then apply the patch version S5820V2_5830V2-CMW710-R2208P01H03.
边栏推荐
- 【经验】win11上安装visio
- Report on the competition status and investment decision recommendations of Guangxi hospital industry in China from 2022 to 2028
- Embedded interview questions (I: process and thread)
- OSPF configuration command of Huawei equipment
- Yygh-11-timing statistics
- [C language syntax] the difference between typedef struct and struct
- MIT6.s081-2020 Lab2 System Calls
- The ECU of 21 Audi q5l 45tfsi brushes is upgraded to master special adjustment, and the horsepower is safely and stably increased to 305 horsepower
- SequoiaDB湖仓一体分布式数据库2022.6月刊
- 27io stream, byte output stream, OutputStream writes data to file
猜你喜欢
SequoiaDB湖仓一体分布式数据库2022.6月刊
清除浮动的方式
局域网同一个网段通信过程
Novice entry SCM must understand those things
Embedded interview questions (IV. common algorithms)
Jushan database appears again in the gold fair to jointly build a new era of digital economy
01. Project introduction of blog development project
H3C V7版本交换机配置IRF
29io stream, byte output stream continue write line feed
59. Spiral matrix
随机推荐
局域网同一个网段通信过程
Baidu online AI competition - image processing challenge: the 8th program of handwriting erasure
[SQL Server fast track] - authentication and establishment and management of user accounts
入侵检测领域数据集总结
ArcGIS application foundation 4 thematic map making
Some easy-to-use tools make your essay style more elegant
B站刘二大人-反向传播
The digital economy has broken through the waves. Is Ltd a Web3.0 website with independent rights and interests?
High quality coding tool clion
【论文阅读】NFlowJS:基于鲁棒学习的合成负数据密集异常检测
【SQL server速成之路】——身份驗證及建立和管理用戶賬戶
Rustdesk builds its own remote desktop relay server
【无标题】
Embedded interview questions (IV. common algorithms)
Implementation of linked list in address book management system
27io stream, byte output stream, OutputStream writes data to file
05. Security of blog project
Problems encountered in installing mysql8 on MAC
B站刘二大人-数据集及数据加载 Lecture 8
J'ai un chaton.