当前位置:网站首页>Project cost management__ Cost management technology__ Article 6 prediction
Project cost management__ Cost management technology__ Article 6 prediction
2022-07-03 09:42:00 【ximanni18】
Techniques and tools for project cost management Include :
- Cost analysis technology
- Cost management technology
This paper introduces the cost management technology The first 6 spot
6. forecast
As the project progresses , In the project team, according to the project performance , Estimate of completion (EAC) To make predictions , The predicted results may be consistent with the completion budget (BAC) Differences exist . If BAC Obviously no longer feasible , Then the project manager shall consider EAC To make predictions . forecast EAC Based on current performance information and other knowledge , Predict the future situation and events of the project . The forecast shall be generated according to the work performance data provided during project implementation 、 Update and republish . Job performance information includes the past performance of the project , And any information that may have an impact on the project in the future .

In the calculation EAC when , Usually the actual cost of the work done , Add the remaining work The completion of the project needs to be estimated (ETC).
The bottom-up aggregation method manually carried out by the project manager and the project team , Is one of the most common EAC Prediction method .
The formula : EAC= AC+ Bottom up ETC. namely Completion estimate = actual cost + The bottom-up completion needs to be estimated .
~~~~~~~~~~~~~~~~~~~~~~~~~
Calculation EAC ( Completion estimate ) There are three most commonly used methods :
1 It is assumed that... Will be completed at the budgeted unit price ETC Work . This approach recognizes the cumulative actual project performance expressed in realized costs , And predict all the future ETC All work Will be completed at the budgeted unit price .
The formula : EAC=AC+(BAC-EV).
2. Assume that at present CPI complete ETC Work . This approach assumes that the project will continue as it has been so far , namely ETC The work will be based on the cumulative cost performance index of the project to date (CPI) The implementation of .
The formula : EAC= BAC/CPI
CPI: Cost performance index , CPI = EV / AC.
3. hypothesis SPI And CPI Will also affect ETC Work . In this prediction , It is necessary to calculate an efficiency index determined by cost performance index and schedule performance index , And suppose ETC The work will be completed according to the efficiency index . If the project schedule is right ETC Have an important influence . This method is the most effective . When using this method , It can also be judged by the project manager , Give to separately CPI and SPI Give different weights , Such as
80/20, 50/50 etc. .
The formula : EAC = AC+[(BAC-EV) / (CPI x SPI )].
If predicted EAC The value is not within the acceptable range , Is to send an early warning signal to the project management team .
边栏推荐
- 顺利毕业[3]-博客系统 更新中。。。
- [CSDN] C1 training problem analysis_ Part II_ Web Foundation
- UCI and data multiplexing are transmitted on Pusch (Part VI) -- LDPC coding
- LeetCode每日一题(2090. K Radius Subarray Averages)
- [combinatorics] Introduction to Combinatorics (combinatorial thought 2: mathematical induction | mathematical induction promotion | multiple induction thought)
- Flink learning notes (VIII) multi stream conversion
- [csdn] C1 analyse des questions de formation Partie III Bar _ JS Foundation
- 基于opencv实现桌面图标识别
- Call the contents of Excel cells opened at the same time - button line feed
- Please tell me how to set vscode
猜你喜欢

全球KYC服务商ADVANCE.AI 活体检测产品通过ISO国际安全认证 产品能力再上一新台阶

NR technology -- MIMO

Win10安装ELK

LeetCode每日一题(2212. Maximum Points in an Archery Competition)

Runtime.getRuntime().gc() 和 Runtime.getRuntime().runFinalization() 的区别
![[CSDN]C1训练题解析_第二部分_Web基础](/img/91/72cdea3eb3f61315595330d2c9016d.png)
[CSDN]C1训练题解析_第二部分_Web基础

Intelligent home design and development

Matlab reads hexadecimal numbers and converts them into signed short

STM32 interrupt priority management

Design and development of biological instruments
随机推荐
Jestson Nano自定义根文件系统创建(支持NVIDIA图形库的最小根文件系统)
Flink learning notes (10) Flink fault tolerance mechanism
QT qstring:: number apply base conversion
开学实验里要用到mysql,忘记基本的select语句怎么玩啦?补救来啦~
Analysis of the implementation principle of an open source markdown to rich text editor
Arduino handles JSON data, arduinojson assistant
Electronic product design, MCU development, circuit cloning
Leetcode daily question (931. minimum falling path sum)
[successful graduation] [1] - visit [student management information system]
Chromium Embedded Framework (CEF) 介绍
Flink learning notes (IX) status programming
Learn the contents of 5g toolbox supporting NR through the NR resources provided by MATLAB
NR PUCCH format0 sequence generation and detection mechanism
Install local sources using yum
Spark cluster installation and deployment
Flink learning notes (VIII) multi stream conversion
Usage of pandas to obtain MySQL data
软件测试工程师是做什么的 通过技术测试软件程序中是否有漏洞
[combinatorics] Introduction to Combinatorics (context of combinatorics | skills of combinatorics | thought of combinatorics 1: one-to-one correspondence)
The number of weak characters in the game (1996)