Project cost management__ Cost management technology__ Article 6 prediction
2022-07-03 09:42:00 【ximanni18】
Techniques and tools for project cost management Include :
- Cost analysis technology
- Cost management technology
This paper introduces the cost management technology The first 6 spot
6. forecast
As the project progresses , In the project team, according to the project performance , Estimate of completion (EAC) To make predictions , The predicted results may be consistent with the completion budget (BAC) Differences exist . If BAC Obviously no longer feasible , Then the project manager shall consider EAC To make predictions . forecast EAC Based on current performance information and other knowledge , Predict the future situation and events of the project . The forecast shall be generated according to the work performance data provided during project implementation 、 Update and republish . Job performance information includes the past performance of the project , And any information that may have an impact on the project in the future .
In the calculation EAC when , Usually the actual cost of the work done , Add the remaining work The completion of the project needs to be estimated (ETC).
The bottom-up aggregation method manually carried out by the project manager and the project team , Is one of the most common EAC Prediction method .
The formula : EAC= AC+ Bottom up ETC. namely Completion estimate = actual cost + The bottom-up completion needs to be estimated .
~~~~~~~~~~~~~~~~~~~~~~~~~
Calculation EAC ( Completion estimate ) There are three most commonly used methods :
1 It is assumed that... Will be completed at the budgeted unit price ETC Work . This approach recognizes the cumulative actual project performance expressed in realized costs , And predict all the future ETC All work Will be completed at the budgeted unit price .
The formula : EAC=AC+(BAC-EV).
2. Assume that at present CPI complete ETC Work . This approach assumes that the project will continue as it has been so far , namely ETC The work will be based on the cumulative cost performance index of the project to date (CPI) The implementation of .
The formula : EAC= BAC/CPI
CPI: Cost performance index , CPI = EV / AC.
3. hypothesis SPI And CPI Will also affect ETC Work . In this prediction , It is necessary to calculate an efficiency index determined by cost performance index and schedule performance index , And suppose ETC The work will be completed according to the efficiency index . If the project schedule is right ETC Have an important influence . This method is the most effective . When using this method , It can also be judged by the project manager , Give to separately CPI and SPI Give different weights , Such as
80/20, 50/50 etc. .
The formula : EAC = AC+[(BAC-EV) / (CPI x SPI )].
If predicted EAC The value is not within the acceptable range , Is to send an early warning signal to the project management team .
边栏推荐
- Leetcode daily question (745. prefix and suffix search)
- [combinatorics] Introduction to Combinatorics (combinatorial thought 2: mathematical induction | mathematical induction promotion | multiple induction thought)
- Learning C language from scratch -- installation and configuration of 01 MinGW
- Development of electrical fire system
- NR technology -- MIMO
- PolyWorks script development learning notes (I) - script development environment
- Design and development of biological instruments
- Runtime.getRuntime().gc() 和 Runtime.getRuntime().runFinalization() 的区别
- LeetCode每日一题(968. Binary Tree Cameras)
- Please tell me how to set vscode
猜你喜欢
Intelligent home design and development
一款开源的Markdown转富文本编辑器的实现原理剖析
Nodemcu-esp8266 development (vscode+platformio+arduino framework): Part 2 --blinker_ Hello_ WiFi (lighting technology - Mobile App control routine)
What do software test engineers do? Pass the technology to test whether there are loopholes in the software program
[successful graduation] [1] - visit [student management information system]
[CSDN] C1 training problem analysis_ Part II_ Web Foundation
Runtime.getRuntime().gc() 和 Runtime.getRuntime().runFinalization() 的区别
[CSDN] C1 training problem analysis_ Part IV_ Advanced web
Leetcode daily question (1162. as far from land as possible)
【男保姆式】教你打开第一个微信小程序
随机推荐
数字身份验证服务商ADVANCE.AI顺利加入深跨协 推进跨境电商行业可持续性发展
[csdn] C1 analyse des questions de formation Partie III Bar _ JS Foundation
制作jetson nano最基本的根文件系统、服务器挂载NFS文件系统
Patent inquiry website
Leetcode daily question (2232. minimize result by addressing parents to expression)
MySQL environment variable configuration
[successful graduation] [1] - visit [student management information system]
numpy. Reshape() and resize() functions
Leetcode daily question (2109. adding spaces to a string)
UCI and data multiplexing are transmitted on Pusch - Part I
Learning C language from scratch -- installation and configuration of 01 MinGW
LeetCode每日一题(2090. K Radius Subarray Averages)
Leetcode daily question (931. minimum falling path sum)
基于opencv实现桌面图标识别
Development of fire power monitoring system
Nr--- Pusch I: sorting out the agreement process
Solve editor MD uploads pictures and cannot get the picture address
顺利毕业[2]-学生健康管理系统 功能开发中。。。
[graduation successful] [1] - tour [Student Management Information System]
PIP configuring domestic sources